01/14/11-SOSS submitted.
01/21/11- Bert Watts forwarded the new Contractor Safety and Health Specification section that is to be included in all future HCFD project manuals.
01/24/11-SOSS signed by BOCC and issued to GBBN along with Purchase Order.
01/25/11- Modified Standard Bidding Documents to indicate Christian Sigman as Interim County Administrator.
01/27/10-Attended HCFD Partnership monthly partner meeting.
01/27/11- GBBN forwarded to the other Partners the revised Master Specification Table of Contents and Legal Wrap showing the inclusion of the new Contractor Safety and Health specification section.
02/04/11- The meeting with Amy Hoh to kick-off a new project to modify the existing office partitions was cancelled.
02/14/11-Kick-off meeting with Sean Winfield of CAGIS to initiate an estimate to enlarge the CAB 10th Floor Conference Room.
02/15/11- Bert Watts agreed to perform the CAGIS work under this contract in lieu of a SOSS.
02/18/11- Drawings and estimate for CAGIS project sent to Bert Watts.
02/24/11- Attended the regularly schedule Partnering meeting at the Courthouse.
03/12/11- Met with Bert Watts to review the as-built conditions at Parkhaus Retail spaces. GBBN took measurements and photographs of space
03/15/11- GBBN sent as-builts to Bert Watts for review. Additional MEP input to be performed by GBBN due to lack of involvem,ent by ThermalTech.
03/25/11- Meeting with GBBN, ThermalTech and Duke Energy to discuss potential energy savings and partnering programs.
03/31/11- Attended the regularly schedule Partnering meeting at the Courthouse.
04/28/11- Attended the regularly schedule Partnering meeting at the Courthouse.
05/11/11- Interior Project Management performed background checks at the Justice Center. GBBN delivers results to Diana Supe.
05/12/11- GBBN staff performed background checks at Justice Center. GBBN delivered results to Diana Supe.
05/26/11- Attended the regularly schedule Partnering meeting at the Courthouse.
06/23/11- Corrections for new County Administrator made to standard front-end specifications.
06/30/11- Attended the regularly schedule Partnering meeting at the Courthouse.
– Website updated after Partnering Meeting.
07/06/11- Meeting with ThermalTech to review Courthouse Courtroom Ceilings for redesign of the soffits and ceilings with Tony Matre.
07/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.
– Website updated before Partnering Meeting.
08/25/11- Attended the regularly schedule Partnering meeting at the Courthouse.
– Website updated before Partnering Meeting.
09/29/11- Attended the regularly schedule Partnering meeting at the Courthouse.
– Website updated before Partnering Meeting.