by MCB MCB

05/29/19 – Hamilton County requests SOSS for project.

06/26/19 – TEI submits SOSS to facilities.  Project Pending SOSS approval and PO.

07/24/19 – Project pending SOSS approval and PO.

08/27/19 – Project pending SOSS approval and PO.

09/25/19 – Project Pending SOSS approval and PO.

10/30/19 – Project Pending SOSS approval and PO.

12/11/19 – Project Pending SOSS approval and PO.

01/28/20 – Project Pending SOSS approval and PO.

02/26/20 – TEI receives signed SOSS and PO for project.  TEI contacts Jessica Powell and requests project kickoff with 2020 staff.  Kickoff meeting to occur ASAP and project to commence thereafter.

03/26/20 – TEI, County Facilities, and building manager meet to kick off the project.  Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.

04/30/20 – Project Pending COVID-19 restrictions.

05/27/20 – Project pending COVID-19 restrictions.