08/11/10 – Schematic Design submitted to owner with cost. Project is canceled due to cost.

05/26/10 – SOSS approved. We will setup fieldwork and kickoff next week. Cost estimate complete. Project put on hold because of pricing.

04/26/10 – Schematic Drawing is complete. Fieldwork is complete for SD. We are working on cost estimate to send with SD.

03/23/10 – Project on hold.

01/26/10 – Bert contacted ThermalTech about permit requirements and was told the mechanical code would require a permit for the new ventilation calc required in a new conference room. Bert has the SOSS for this project.

12/31/09 – Bert contact TEI to work on this project and renovation. TEi owes Bert an SOSS based on the HamCo Scope of Work.