by TEI TEI

Project Lead: THP – F79

06/06/16 – As part of the plans review the city required special inspections for both concrete testing and soil investigation.

06/14/16 – THP submitted an SOSS with Terracon completing the special inspection.

06/21/16 – County approved SOSS.

08/25/16 – Refer to F66 for updates.

01/26/17 – City requires extra paperwork from Terracon before they can final the permit on this job.

07/27/17 – City closed out permit for this project. All wrapped up. Ready to Archive.