by TEI TEI

03/30/11 – This project is complete. TEI finalized the HVAC permit and paid for it at the City of Cincinnati so EDI can close out this project.

03/02/11 – TTC checked on braided hose install by EDI on humidifier. Brady said they are working on this. TTC review wall mounted installation and there is no good way to clean this install up with a simple product. TTC asked EDI to closeout project and send in final payapp.

12/30/11 – TEI released the punchlist on the project today.

12/15/10 – EDI on board and working on project towards punchlist completion