by TEI TEI

Project Lead: GBBN – F079

03/23/17 – At Partnering Meeting Facilities explains project scope and requests SOSS.

03/24/17 – GBBN corresponds with Bayer Becker requesting proposal for partial survey and staking services.

04/07/17 – Bayer Becker sends proposal to GBBN.

04/10/17 – GBBN authors and delivers SOSS to Facilities.

07/17/17 – Bayer Becker has completed all field work.  The next step will be completing the survey drawing and staking the property line for the fence installation.  This should be completed by the end of the month.

07/26/17 – Bayer Becker sends GBBN a sign and sealed survey for use by the Owner.  Missing monuments and two sets foe nails have been installed on site for use in locating the fencing by Others.

10/23/17 – GBBN receives invoice from Bayer Becker for survey.