by TEI TEI

Project Lead: THP

06/01/12 – THP submitted SOSS.

09/13/12 – County approves SOSS.

10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.

10/31/12 – THP working on DD documents.

01/15/13 – THP Issued DD documents for review. Documents part of façade repair project as alternate.

09/25/13 – REFER to F39 for project status.

12/09/15 – Project on hold. Projected construction 2017