by Champlin Champlin

10/16/19 – County made request for get pricing to bid out painting 250 William Howard Taft – first floor only.
10/25/19 – Champlin was at site for field verification.
12/5/19 – Cost Estimate and SD drawings sent to County
12/10/19 – Cost Estimate Revised
01/9/20 – SOSS submitted to county
01/22/20 – Approved SOSS and PO received by Champlin
01/30/20 – Waiting to receive bid schedule approval and list of approved vendors before sending RFP to potential bidders
02/21/20 – bid documents sent to County for approval
03/11/21 – Documents revisions sent to Champlin
03/18/20 – Bid documents sent to county
04/02/20 – Project put on hold due to Covid-19
06/25/20 – County reported that most of this work was completed in house.