04/09/19 – Champlin receives request for Master Planning proposal
06/24/19 – Master Planning Kick-Off meeting held at Courthouse
07/02/19 – Champlin sends initial Master Planning Form to County Facilities
07/22/19 – Champlin sends revised Master Planning Form to County Facilities
08/05/19 – Master Planning Form and Master Planning Department Meetings reviewed at meeting held at Courthouse with County Facilities
08/20/19 – Champlin met with Moira Weir and Michael Patton, JFS
08/20/19 – Champlin met with Todd Lang, County Engineer
08/22/19 – Champlin met with Greg Brush, Clerk of Courts
08/23/19 – Champlin met with Dave Pittinger, Recorder
08/27/19 – Champlin met with Michael Lonneman, Treasurer
08/27/19 – Champlin met with Ray Faller, Public Defender
08/29/19 – Champlin met with Adult Probation
08/30/19 – Champlin met with Frank Spatero & Sarah Irwin, HR
09/03/19 – Champlin met with Trina Jackson, Re-Entry
09/03/19 – Champlin met with Paula Drake, Auditor
09/05/19 – Champlin met with James Noyes, Planning & Development
09/05/19 – Champlin met with John Hetzel & Dale Wittmer, Sheriff (800 Broadway & JFS)
09/06/19 – Champlin met with Carla Guenther & Steve Rokich, Juvenile Court
09/06/19 – Champlin met with Lisa Gorrasi & Bev Davis, Domestic Relations Court
09/12/19 – Juvenile Courts tour as follow up to 09/06 meeting
09/12/19 – Champlin met with Joann Cramer, Purchasing
09/13/19 – Champlin met with John Hoffman, Telecommunications
10/25/19 – Master Plan Draft Presentation and Review with Master Planning committee
11/12/19 – Champlin met with Bert Watts and Tony Matre to discuss Master Plan Draft.
11/26/19 – Champlin submitted Master Plan Document. Financial review section still under review.
12/08/19 – Champlin received comments on the 11/26 document from Bert Watts.
12/13/19 – Champlin submitted final version of Masterplan to County
02/20/20 – Champlin received final comments. Updated master plan accordingly
05/12/20 – Final draft submitted to Bert.