by Champlin Champlin

02/14/19 – County invites Champlin for MSA agreement
02/21/19 – County sent MSA Contract to Champlin
03/13/19 – County sent revised MSA Contract to Champlin
03/18/19 – Champlin sent proposed revisions to MSA Contract
03/29/19 – County sent final MSA Contract
05/23/19 – General Services P.O. approved
05/30/19 – Kru and Mike from Champlin attended Monthly Partners Meeting
06/03/09 – Bert requests code interpretation for safe room locks on certain areas within the 911 Communications Center.
06/07/19 – Champlin provides 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/14/19 – Champlin provides further clarifications on 2017 OBS interpretation for safe room locks on certain areas within the 911 Communications Center
06/27/19 – Kru from Champlin attended Monthly Partners Meeting
07/31/19 – Christy from Champlin attended Monthly Partners Meeting.
08/29/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
09/26/19 – Kru from Champlin attended Monthly Partners Meeting and updated website.
10/30/19 – Champlin visited Auto Title and currently working on space layout.
12/12/20 – Mike and Sam from Champlin attended Monthly Partners Meeting and Updated website
01/02/20 – Bert reached out to Mike and Kru for CAB signage replacement
01/10/20 – Kru and Sam from Champlin visit Taft Center for potential Alley Door Upgrade
01/24/20 – Champlin reached out to multiple vendors for information on existing conditions
01/28/20 – Champlin received CAD files of CAB elevations from THP.

01/30/20 – Mike and Sam attended Monthly Partners Meeting and updated website.

01/30/20 – CAB signage project to be added to an existing facade repair job currently active at the CAB

02/04/20 – Signage drawings sent to THP to give to AFR