by THP THP

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/01/19 – THP met with Owner and Contractor for preconstruction meeting and issued meeting notes.
08/12/19 – THP reviewed and returned submittals received 8/7/19 from Contractor.
08/14/19 – THP reviewed and returned revised submittals from Contractor.
08/19/19 – THP met with Owner and Contractor for first progress meeting and issued meeting notes.
08/20/19 – THP met with Darnell at 800 Broadway to review additional façade issues to be reviewed for repair.
08/22/19 – THP met Contractor at 800 Broadway to review and document completed stone patch preparation progress and stone patch mockups.
08/23/19 – THP issued field report 1.
08/23/19 – THP had telephone conversations with Owner and Contractor to discuss status of mortar joint tuckpointing quantities relative to unit cost allowance amounts.
08/26/19 – THP met with Owner and Contractor for weekly progress meeting and issued meeting notes.
08/26/19 – THP reviewed pencil copy of Contractor’s first application for payment.
08/28/19 – THP visited 800 Broadway to meet Contractor, review progress, and do close-up inspection of south elevation in the area of the façade near the office where leaks have been an ongoing issue.
08/29/19 – THP directed Contractor to install two additional stone patch samples at 800 Broadway west elevation.
08/29/19 – THP reviewed and approved Contractor’s first application for payment.
08/30/19 – THP delivered application for Payment to HC.
08/30/19 – THP visited 800 Broadway to observe and document additional stone patch samples.
09/03/19 – THP issued field reports 2 & 3 from 8/28 & 8/30 site visits.
09/06/19 – THP visited 800 Broadway to meet Contractor and review progress.
09/09/19 – THP developed Change Order 1.
09/09/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/09/19 – THP met Contactor and American Scaffolding at 800 Broadway to review access for pricing repairs at southwest corner of tower.
09/09/19 – Change Order #1 for survey of A&D façade was approved and signed by Owner and Contractor.
09/09/19 – THP issued field report 4  from 9/6 site visit.
09/10/19 – THP issued notes from 9/9 progress meeting.
09/16/19 – THP developed Change Orders 2 & 3.
09/16/19 – THP met Owner and Contractor at CAB for progress meeting.
09/16/19 – Change Orders #2 for Justice Center façade repairs and #3 for 800 Broadway tower spall repair were approved and signed by Owner and Contractor.
09/17/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and identify additional repair areas.
09/18/19 – THP issued notes from 9/16 progress meeting.
09/20/19 – THP reviewed pencil copy of Contractor’s second application for payment and had conversation with Owner about use of unit cost allowances to cover additional façade repairs requested by HC at CAB.
09/20/19 – THP issued field report 5 from 9/16 site visit.
09/23/19 – THP met Owner and Contractor at CAB for progress meeting and issued meeting notes.
09/23/19 – THP reviewed and approved Contractor’s second application for payment.
09/23/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and document conditions at terra cotta excavation.
09/24/19 – THP issued field report 6 from 9/23 site visit.
09/28/19 – THP visited site at 800 Broadway to document progress of limestone removal at west elevation.
09/30/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/30/19 – THP visited site at 800 Broadway to document conditions of masonry backup wall at west elevation.
10/01/19 – THP issued notes from 9/30 progress meeting.
10/02/19 – THP met Contractor at THP to review conditions of backup wall at 800 Broadway and discuss details for installation of wall ties.
10/02/19 – THP had telephone conversation with Owner to discuss recommendation to demolish and rebuild a portion of the backup wall at the west elevation at 800 Broadway.
10/02/19 – THP issued field report 7 from 9/30 site visit.
10/02/19 – THP developed letter outlining effect of additional work at backup wall on overall schedule at 800 Broadway.
10/07/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/07/19 – THP issued notes from progress meeting.
10/07/19 – THP developed Cash Allowance Usage 1 and emailed to Owner and Contractor for review and approval.
10/07/19 – THP visited site at 800 Broadway to review and document progress of backup wall modifications at 800 Broadway.
10/08/19 – THP issued field report 8 from 10/7 site visit.
10/14/19 – THP met Owner and Contractor at WH Taft Center for progress meeting.
10/15/19 – THP issued notes from 10/14 progress meeting.
10/16/19 – THP met Contractor at WH Taft Center to review and document progress, then visited 800 Broadway and CAB to document completed work.
10/19/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/20/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/21/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/21/19 – THP issued field report 9 from 10/16 site visit.
10/21/19 – THP issued notes from progress meeting.
10/25/19 – THP reviewed and approved Contractor’s third application for payment.
10/25/19 – THP issued field report 10 from 10/19 & 10/20 site visits.
10/28/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/29/19 – THP met Contractor at CAB to document progress of GFRC installation, then visited 800 Broadway and WH Taft Center to document completed work.
10/29/19 – THP issued noted from 10/28 progress meeting.
12/31/19 – THP reviewed and approved AFR’s fifth application for payment.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/07/20 – THP delivered AFR’s fifth application for payment to BW.
01/07/20 – THP finalized and emailed letters to city about completion of façade repairs at CAB, 800 Broadway, and WHT Center.
01/13/20 – THP reviewed AFR closeout documents and discussed requirements with BW and AFR.
01/21/20 – THP developed and issued change order #5 for trench drain repairs at 250 WHT.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs at Justice Center and 2020 Auburn Ave.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/24/20 – THP received and reviewed AFR’s revised closeout documents and forwarded to BW for approval.
01/28/20 – THP reviewed and approved AFR’s sixth application for payment.
01/30/20 – THP delivered AFR’s sixth application for payment to BW.
02/04/20 – THP received Champlain Architecture drawing for CAB signage change and forwarded to AFR for change order proposal.
02/10/20 – THP received and reviewed change order proposal from AFR for CAB signage change, and forwarded to BW for review and approval.
02/12/20 – THP developed AIA G701 Change Order #6 for 250 WHT plumbing repairs and emailed to AFR for review and signature.
02/18/20 – Change Order #6 signed by AFR and BW.
02/20/20 – THP visited site at 250 WHT to observe and document progress of trench drain replacement at Bellevue Ave. entrance.
02/21/20 – THP developed AIA G701 Change Order #7 for CAB signage change and emailed to AFR for review and signature.
02/24/20 – Change Order #6 signed by AFR.
04/06/20 – THP visited 250 WHT to observe and document prep of south trench drain prior to concrete pour.
04/09/20 – THP issued Field Report #24 documenting 250 WHT trench drain repairs.
04/22/20 – THP visited Todd A. Portune Center, Alms & Doepke, and 250 WHT to document repairs.
04/24/20 – THP issued Field Report #25 documenting completion of repairs at Alms & Doepke and 250 WHT, and completion of coating at removed CAB letters.
04/28/20 – THP reviewed pencil copy of AFR’s 9th application for payment, and replied with markups about revisions for line items related to change order #8.
04/28/20 – THP had conversation with BW about signage company’s request for payment on new signage letters.
04/29/20 – THP requested and received photographs of letters in storage at signage subcontractor’s warehouse.
04/30/20 – THP signed AFR’s 9th application for payment and forwarded to BW.
06/25/20 – 2020 Auburn, and 230 E 9th/WH Taft Center are still waiting for final approval of completed façade repairs by city.
06/25/20 – Justice Center is closed as of 3/27/20. A&D sill repairs and 250 WHT trench drains are complete. CAB signage removed and repairs are complete, but the installation of the new Todd B. Portune Center for County Government letters has been put on hold.
07/30/20 – Portune letters still on hold.