by THP THP

October 26, 2011 Update THP develops test repair options and met with SSRG to review for pricing. THP to submit separation SOSS for contractor work.

Past Comments

Due to findings, weather sensitive repairs, and schedule; THP proposed completing a safety survey and trial repairs. County requested a letter report summarizing needed work to be possibly incorporated into a larger 2012 project. A SOSS for the letter reported was requested.

September 23, 2011 THP met with County to review conditions of roof.

Early September THP completed field review and design analysis.

August 3, 2011 SOSS approved.

July 18, 2011 THP Submitted SOSS for review.