03/20/07 – Check CRA website for closeout documents. Project is ready for archiving.

02/19/07 – Coordinate with CRA for final details. Project is nearly complete.

01/22/07 – Permit drawings have been submitted to the IBI

01/02/07 – TTC and Spencer discussed the project today and TA and TTC will kickoff the project internally on 01/03/07 and push it towards compeltion.

11/10/06 – They installed the desk. Flooring will be installed in the next several weeks.

09/08/06 – Preconstruction meeting held. Things went as planned.

04/05/06 – Review meeting is scheduled for this Friday. Cost estimates have been given to the client. No HVAC or Plumbing work on this job.

03/08/06- Mike Stiles met with the architect on this project for kickoff.