by TEI TEI

Project Lead: THP

06/01/12 – THP submitted SOSS.

09/13/12 – County approves SOSS.

10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.

10/31/12 – THP working on DD documents.

01/15/13 – THP Issued DD documents for review.

02/08/13 – County returned project manual comment.

02/19/13 – THP and County had a design review meeting.

05/17/13 – THP issued 95% Review documents to the County.

06/27/13 – Project update. Due to weather sensitive work, if project approved work will not occur until next spring. Possible bid project late 2012.

10/31/13 – Project on hold.

01/30/14 – Project on hold.

04/24/14 – Project on hold.

06/26/14 – Project on hold.

07/31/14 – Project on hold.

08/27/14 – Project on hold.

09/25/14 – Overall project on hold.

01/29/15 – Overall project on hold.

02/26/15 – Overall project on hold.

03/26/15 – Overall project on hold

04/01/15 – THP requested to assess current roof condition and provide a summary report letter.

04/17/15 – THP published roof assessment letter with updated opinion of probable cost.