02/20/18 – ThermalTech met with the facilities department and A&D staff to discuss the need for a study for the existing access control system. ThermalTech submits SOSS for study for the project. Project pending the approval of the SOSS and PO.
03/27/18 – Project Pending approval of SOSS and PO.
04/25/18 – Project pending approval of SOSS and PO.
05/30/18 – Project Pending approval of SOSS and PO.
06/29/18 – Project Pending approval of SOSS and PO.
07/25/18 – Project Pending approval of SOSS and PO.
08/29/18 – ThermalTech receives approved SOSS and PO (5778030). ThermalTech, Facilities and JFS conduct study kick-off meeting on 08/28/18 and schedule field investigation of 09/13/18. ThermalTech beginning code research and product research beginning 09/01/18.
09/26/18 – ThermalTech completes field investigation with JFS (Claude Toulsen). Report is in progress. ThermalTech to send draft copy to BW for review upon completion.
10/23/18 – ThermalTech working to complete draft of report, and will send to BW and CT for review by 11/09/18.
11/28/18 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
01/29/19 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
02/26/19 – ThermalTech reached out to Basis of Design (VAX) for final pricing, and opinions of probable cost in report pending reciept of the pricing from the supplier. NOTE – Supplier local rep resigned and has not been replaced to date. TEI communicated with corporate offices.
03/26/19 – ThermalTech issues report to HamCo facilities and Claude Toulsen for review and comments. ThermalTech receives comments from BW, and final issuance pending comments from CT.
04/24/19 – Issuance of final report pending receipt of comments from Claude Toulsen.