by TEI TEI

04/13/07 – TE has completed their portion of this project.

04/06/07 – Labels are complete and have been delivered. Clarification Report and CD containing pdf’s of the labels has also been delivered.

03/30/07 – Labels have been delivered to the printer. Awaiting return of labels; delivery expected for the first week of April.

03/23/07 – Project is progressing as expected. Completion by the end of March 07 will be met.

03/20/07 – EDSA modeling in continuing. Project will be complete by end of March.

03/14/07 – NR created project journal and filled in back data from previous meetings. Project progressing, model has been developed, final review of modeling is underway. Project completed date of 03/30/07 is not an issue at this point.