by MCB MCB

03/29/16 – Bert Watts requested a SOSS for a wireless network study for all floors of the building (Sub-basement through 7th floor). ThermalTech issues SOSS. Project pending approved SOSS and PO.
04/27/16 – TEI receives approved SOSS and PO. TEI, Bert Watts, John Nester, Claude Toulsen and Mark Miller have kickoff meeting to discuss existing conditions and JFS desired WiFi parameters. JFS investigating with the state network possibility to add to state network hardware.
05/25/16 – TEI conducts walk through of the building with Claude Toulsen. Identified locations of existing WAP’s, Identified proposed locations for new WAP’s, discussed state requirements and standards, and Claude T to forward to TEI state requirements and recommendations.
06/27/16 – ThermalTech working with Claude Toulsen to identify the state requirements for the system components. The State standards and the county standards do not match. Although JFS is not mandated to utilize the state standard equipment, CT would like to know the implications of using that equipment (cost, etc). ThermalTech to provide costing data for both the state and the county standard systems and make recommendations accordingly.
07/27/16 – TEI meeting with Claude Toulsen on 7/27/16 for progress meeting. The state equipment supplier (Aruba) has been non-responsive for weeks when I have made attempts to contact them for technical support. TEI to discuss this with CT and we are recommending that JFS utilize the Fortinet (county standard equipment) versus the Aruba.
08/23/16 – TEI to submit to Claude Toulsen and Bert Watts final draft of report for final comments and distribution by 8/31/16.
09/28/16 – TEI received final comments from Bert Watts, pending comments from Claude Toulsen for final distribution.
10/25/16 – TEI received final comments from Claude Toulsen – will conclude study portion of project.
01/25/17 – TEI submits SOSS for implementation of report recommendations. Project Pending approval of SOSS and PO.
02/22/17 – TEI receives approved SOSS and PO for the project. Project kick off meeting scheduled with Facilities and JFS on 2/23/17 at 2:00 PM.
03/22/17 – TEI performs field work and finds existing spare breakers in panels on each floor to provide power to the network switches and the WAPs that are a part of the project. Working on Construction cost estimates to have ready for discussion at 04/06 design meeting.
04/26/17 – ThermalTech has meeting with JFS staff and Facilities. TEI completing Bid Docs for Final design review meeting by end of April. TEI to request meeting first week of May to provide final review and establish bid parameters.
05/22/17 – ThermalTech and facilities meets with JFS staff. TE and Facilities presents the HamCo telecom group policies to JFS staff. JFS staff to meet independently and return to TE and facilities with direction that they wish to pursue. TE waiting on final design criteria from JFS IT staff.
06/27/17 – ThermalTech to coordinate with Purchasing, JFS and facilities for dates to put in the ITB. ITB to be issued ASAP. Hold until funding is in place.
07/25/17 – Project on HOLD until funding is in place.
08/28/17 – Project on HOLD until funding is in place.
08/31/17 – Redo entire business model so telephone support will be more prevalent. Wi-Fi not required. BW will set something up in the future.
09/26/17 – project to be completed in conjunction with the furniture/painting project.
05/30/18 – project to be completed in conjunction with the furniture/painting project.
11/28/18 – project to be completed in conjunction with the furniture/painting project.
01/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
03/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
04/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
05/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
06/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
07/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
08/27/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
09/25/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/30/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/31/19 – Move project to Archive, its in the A&D Interior finishes projects.