by TEI TEI

Partner Lead: ThermalTech

03/04/13 – SOSS submitted to Bert.

04/24/13 – SOSS approved and PO issued to ThermalTech. ThermalTech to schedule Kickoff meeting with Bert Watts to establish schedule.

6/26/13 – TEI has sent drawings to HamCo for review. Need to discuss HamCo comments and issue for bids.

08/28/13 – Pre-Bid meeting conducted on 8/28/13. It was observed that (2) fiber optic data cables were already installed from the data rack in the closet by the freight elevator to the A/V cabinet in Room 610.

09/25/13 – Bids received, Phasor Electric is Low Bid. Contracts are into county for approval.

10/30/13 – Phasor to begin work week of November 4.

01/24/14 – Work completed. Phasor to submit final as-built drawings and project can be closed out.

02/25/14 – TEI reviewing as-built drawings. All other close out documents have been turned over to Hamilton County.