08/31/07 – TEI was instructed to put project on hold till next year.

08/08/07 – Project estimated cost seems to be over budget. CRA awaiting direction from Mark Donnelly on scope/cost coordination.

07/30/07 – TE has moved to the design phase of this project.

06/29/07 – TE is awaiting drawings from Cole & Russell. When the drawings arrive TE will put together a cost estimate for the project and present it to Hamilton County Facilities Department.

06/22/07 – TE received word from Cole & Russell that this project is moving forward. TE is now awaiting drawings from Cole & Russell.

06/15/07 – TE is awaiting Joe Merkt, the building manager, to return from vacation so that we can perform the necessary field work to move this project forward.