by TEI TEI

12/26/06 – This project has been put on hold for so long, it is being archived by TTC.

12/14/05 – TE finalized cost estimates for the new phase I work per Cole and Russell’s revised scope. Archibus is up to date. The HVAC scope remains the same because the areas affected are all within our HVAC scope. The electrical is different and Mike Stiles will update the Phase I cost to reflect the smaller scope.

08/05/05 – Diana sent an email stopping all work on this project until the Engineer’s Office releases everyone to do more work. ThermalTech is nearly done with the design at this stoppage point but will hold all work until further notice.