by THP THP

04/10/19 – Engineering office requested a roof replacement project.
04/16/19 – THP visited the site to develop a SOSS.
06/24/19 – THP submitted an SOSS for design services.
07/11/19 – SOSS approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
09/26/19 – Meeting with Burlington Engineer 9/27/19
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/13/19.
11/13/19 – Three bids were received on 11/13/19. Wm. Kramer and Sons was the apparent low bidder.
11/22/19 – THP discussed the bid with Kramer and issued a bid summary letter recommending Kramer complete the work alternates no1 and no2 for $73,764.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/26/20 – County issued executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting early March once formal PO is issued. Work requested to start mid-April. Kramer confirmed start date is good.