by GBBN GBBN

Lead Partner: GBBN

08/17/16 – Facilities confirms GBBN has no As-Built scope for this project on the SOSS.

08/18/16 – GBBN discusses <30% existing structure addition requirement for full existing building structural analysis. GBBN reports findings to Facilities.

08/22/16 – GBBN gets SOSS scope from TEI for Electrical scope of work. Hard copies delivered in the mail.

08/23/16 – GBBN consults with THP to discuss structural SOSS and permitting requirements for the project.

08/24/16 – GBBN forwards contact information from original contractor of Pole Barn Shed for investigation into alternative delivery method.