by MCB MCB

04/24/19 – HCFD requests SOSS from TEI for the project.  TEI submits SOSS and receives signed SOSS and PO.  TEI requests kickoff meeting the HCFD and all parties .  Project start pending project kickoff meeting.

05/29/19 – Design progressing and TEI anticipates that 100% documents will be issued to HamCo no later than mid week (week of June 3).

06/26/19 – Drawing submitted to HamCo for review and no comments received.  TEI submits to IBI for plan review and permit on 06/28/19.

07/24/19 – TEI receives plan review approval from IBI, and secures the electrical permit for trades to work on the project.  Core drills complete and trades working on electrical modifications for the project.  Hamilton County trades to notify ThermalTech when they are ready for the rough in inspection.

08/27/19 – work completed , inspections passed, and the security scanners have been relocated.