by TEI TEI

Refer to TTE for final closeout status.

March 7, 2011 THP published review of completed stone work.

Work complete in late February.

Once approved, THP will close out the project.

March 3, 2011 THP completed review of work and sealant work is acceptable. THP did not see the installation, but received written confirmation that backer rod and shims are installed in the joint.

January 27, 2011 County approved contract. Ram reviewing contract with corporate office. Ram insurance paperwork submitted and approved.

December 28, 2010 Preconstruction meeting occurred.

November 4, 2010 bid received. Thermal Tech and County processing bid.

Prebid meeting completed October 28, 2010.

Prebid meeting scheduled for October 28, 2010.

October 7, 2010 THP sent draft documents to TTE for review.

THP anticipates returning the documents October 7, 2010.

September 28, 2010 THP received draft documents for THP review and design of sealant repairs.

September 2, 2010 provide an email proposal to Thermal Tech to provide consulting services.

August 26, 2010 County, Thermal Tech and THP had kick off meeting to review lighting repair project. THP requested to provide assistance with sealant joint repairs. THP to be a consultant to Thermal Tech.