08/27/19 – County requests onsite meeting to review scope.
09/10/19 – Champlin received approved SOSS & PO.
09/17/19 – Champlin & ThermalTech site visit.
09/27/19 – Check set given to Hamilton County for approval.
10/03/19 – CDs set given to Hamilton County and issued for permit.
12/03/19 – Bulletin #01 sent to County and Triton Services.
12/31/19 – Door and hardware submittals approved and sent to Triton
01/02/20 – CO #4 signed and sent to County
02/03/20 – Champlin performed Punchlist visit
02/04/20 – Punchlist report sent to County and Triton
02/14/20 – Champlin performed Back Punch visit
02/21/20 – Backpunch report sent to County and Triton
05/15/20 – Pay app signed and returned to Triton