06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings
06/17/11 – SOSS submitted in person to Bert Watts.
09/16/11 – Signed SOSS received from Bert Watts.
03/16/12 – GBBN scheduled to meet with Building Manager to begin Field Verification.
08/21/12 – GBBN completes ADA Survey Report. GBBN begins estimating component of the Report.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year.
11/03/15 – GBBN completes Assessment, prints final copies and delivers to Facilities.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects.
06/28/16 – Opinions of Probable Costs for the implementation of the ADA Assessment findings were entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Project Request Estimating.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – Final Project Request Estimates have been printed and ready for insertion into final reports.