by TEI TEI

01/10/07 – Completed in 2006

1/08/07 – NR picked up the panel index binder from Hamilton County Facilities. There are no open issues left on this project. All documents have been turned over to the appropriate parties.

1/03/07 – NR met with Jim Eby of Hamilton County Facilities to review the as-built drawings for this project. The open items were resolved. (3) full sized sets of drawings have been delivered to Hamilton County. The binder containing each panel index is in the possession of Bert Watts. A copy of this binder shall be sent by Bert to ThermalTech Engineering.

1/9/06 – 2nd Floor through Roof is complete. Presently working on the Basement & 1st Floor

12/15/05 – 4th Floor through Roof is complete. Presently working on the 2nd & 3rd Floor

11/15/05 – Roof is complete. Presently working on the 5th Floor