Partner Lead: THP
04/06/15 – County requested SOSS to assess façade and roofs.
04/28/15 – THP developing SOSS.
06/05/15 – THP issued SOSS.
12/08/15 – THP completed roughly 40% of rappelling survey.
01/28/16 – THP completed field survey and working on report.
02/25/16 – THP is working on the report.
04/25/16 – THP complete thermal scans of Courthouse roofs.
04/28/16 – THP anticipates completing the draft report for the County’s review on May 5.
06/19/16 – Draft report complete for THP in house review