by THP THP

05/16/19 – County requested SOSS for façade and roof repair package.
06/19/19 – THP submitted an SOS for design services.
06/27/19 – Verbally approved. Need to final bids and contract by November.
07/03/19 – SOSS Approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
08/29/19 – DD docs to be issued September 13th.
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/19/19.
11/06/19 – Addendum no.1 issued
11/04/19 – Addendume no. 2 issued.
11/21/19 – Three bids were received. Imbus was the apparent low bidder.
11/21/19 – THP discussed the bid with Imbus and issued a bid summary letter recommending Imbus complete the work alternates no1 and no3 for $353,130.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
03/03/20 – THP issued conform set.
03/04/20 – Preconstruction Meeting occurred. Construction to occur once weather allows.
04/16/20 – Imbus mobilized job site.
04/19/20 – Roofing submittals processed.
04/20/20 – Imbus began roof repairs.
05/04/20 – Pay application No.1 processed.
05/12/20 – Lintel submittal processed.
05/27/20 – Pay application No. 2 processed.
06/15/20 – THP issued updated canopy anchor requirements.
06/17/20 – Imbus subcontractor finished installing the canopy.
06/25/20 – Roof work completed. Team plans to meet and punch the roof 6/26/20.
06/26/20 – Punch list review meeting completed. Two minor items noted.
07/08/20 – Warranties submitted.
07/24/20 – Final pay application submitted.
07/27/20 – Changer order No. 1 approved.
07/30/20 – Punch list work complete. THP processing closeout paper work.
12/09/20 – Final project manual submitted.
12/10/20 – THP plans to drop off project manual and final pay request 12/11/20.