by THP THP

05/16/19 – County requested SOSS for façade and roof repair package.
06/19/19 – THP submitted an SOS for design services.
06/27/19 – Verbally approved. Need to final bids and contract by November.
07/03/19 – SOSS Approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
08/29/19 – DD docs to be issued September 13th.
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/19/19.
11/06/19 – Addendum no.1 issued
11/04/19 – Addendume no. 2 issued.
11/21/19 – Three bids were received. Imbus was the apparent low bidder.
11/21/19 – THP discussed the bid with Imbus and issued a bid summary letter recommending Imbus complete the work alternates no1 and no3 for $353,130.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.