by THP THP

06/10/19 – Hamilton County requested SOSS to survey masonry coated area and remove loose debris.
06/12/19 – THP met with American Façade Restoration to discuss contractor scope and to get a proposal.
06/19/19 – THP submitted an SOSS for design services and AFR proposal to complete the work.
08/29/19 – Work scheduled to start after F117 complete.
10/31/19 – See F117 for project status.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.