11/11/18 – GBBN contacted by Director of Operations to review potential two Kitchen Epoxy Floor Replacements. Projects to be constructed by 3/318.
1/11/18 – GBBN contacts manufacturer to inquire about existing product that has begun to fail and preparation required to recoat.
1/21/18 – Samples of colors and slip resistance sent to Operations for selection by Owner.
1/23/18 – Owner color and slip resistance level selections presented to GBBN.
2/1/18- Pre-Bid meeting held at GABP. Three attendees present. RFP documents distributed.
2/3/18 – Addenda #1 distributed.
2/12/18- All three proposals received. GBBN contacts low and responsible bidder to verify scope. GBBN recommends J Wesselman Specialty Flooring, LLC to Owner.
02/19/18 – Contractor to commence work at GABP. Background Checks required by Reds.