08/08/05- C+R sent a preliminary project report to Hillcrest. TE to review and comment and provide updates to Spencer for inclusion.

06/16/05 – C+R, TE and HCDF had a follow up meeting at site to discuss layout issues. Spencer distributed possible floor plans for review. TE went over utilities that were underground and reported that electric, gas and water are all near the expansion area.

01/19/05 – Second Field trip to discuss cost and scope.