by TEI TEI

LEED Partner: THP

03/28/12 – All work complete; except asphalt patch at Courthouse ramp expansion joint. Asphalt patch along joint needs to be replaced. Currently waiting on warmer weather.

04/25/12 – THP requested final punch list schedule from RAM end of March with no response.

5/19/12 – Ram completed asphalt repairs. Ram completing concrete injection work with plans to complete work June 1. Final work is weather dependent.
Ram completed punch list repairs. THP to review status of closeout documentation with Ram.

9/26/12 THP Reviewing closeout status. All construction activities are complete.