by TTC TTC

07/11/19 – ThermalTech Issued SOSS-F-113.
08/21/19 – County issued SOSS and PO to ThermalTech.
10/21/19 – Project Issued for Bidding.
10/28/19 – Prebid held for project.
10/30/19 – TEI working on Addendum 1 questions.
12/12/19 – Project is in for contract and approval. County reports the contract is with the vendor.
01/21/20 – Pre Const held with Andy, TTC and Triton.
01/28/20 – Pre Const meeting notes distributed. CO costing approved by TTC to Marley.
01/29/20 – Triton sent in SOV, project schedule and submittals.
02/24/20 – Triton really pushing for background checks, Tony to check on Monday and let us know. Triton needs to get started very soon to have any chance of getting done even by April 15.
03/24/20 – Triton emailed today that the project has been put on hold for this spring and summer and it will be done in October 2020 due to the government shutdown and delivery orders.
04/27/20 – Material has arrived at Triton. Pictures were sent to ThermalTech for approval for payment of stored materials. Covid-19 has this project on hold for the time being.
05/27/20 – No additional updates this month due to Covid.
06/23/20 – TEI updated the submittals and sent to Triton for the job. Block fill is in the Triton yard and awaiting installation in November 2020. There were a couple of items on the submittal review that Triton will check on with the mfgr. Brent Ernsthausen and Clay are our new PM on this job.
07/29/20 – Triton and Brent back on job, TTE caught up on prep work for these towers with Brent for fall work.
08/26/20 – Discussed paying Triton payapps based on equipment stored in their yard. TTC sent photos along with approved payapp.
09/18/20 – Allowance Usage #1 email out and signed by TTE and Triton, we are awaiting final approval by County.
10/28/20 – Pre Const meeting moved to 11/4/20 1:00 pm.
12/10/20 – CT#2 demo is complete. Crane is scheduled on 12/19 with a street closure anticipated. Triton keeping us up to date with email updates from Clay. The project is proceeding along nicely.
12/28/20 – Verbal approval on extra work for cooling tower C-3 replacements was given. Triton continuing work on the towers and order for new galvanized pans was placed with Stoermer.