08/21/20 – TEI submits SOSS, project pending SOSS approval and PO.
09/23/20 – TEI receives PO and signed SOSS for project. TEI to schedule project kickoff with HCFD.
10/27/20 – TEI Develops costing and recommendations for system replacements. TEI final report pending receipt of Russelectric report from outage for inclusion in final report.
12/09/20 – TEI received Russelectric report – to complete report and send to HCFD final draft.