by MCB MCB

08/21/20 – TEI submits SOSS, project pending SOSS approval and PO.

09/23/20 – TEI receives PO and signed SOSS for project.   TEI to schedule project kickoff with HCFD.

10/27/20 – TEI Develops costing and recommendations for system replacements.  TEI final report pending receipt of Russelectric report from outage for inclusion in final report.

12/09/20 – TEI received  Russelectric report – to complete report and send to HCFD final draft.