by THP THP

Can project be closed out?

March 8, 2011 report entered into Archibus.

March 4, 2011 report sent to County.

THP working on report.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed façade lift inspection during safety survey.

THP working on project.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed facade lift inspection during safety survey.

December 10, 2010 THP completed initial visual survey. Survey revealed loose sandstone and THP recommended completing a knock down survey by a contractor. Due to weather conditions repairs should occur in the spring. THP getting pricing from the contractor.

November 15, 2010 SOSS approved.

October 26, 2010 THP submitted SOSS for review.

October 26, 2010 THP and County completed kick off meeting.

October 19, 2010 County requested SOSS from THP.

August County and THP discussed preliminary Memorial Hall assessment numbers.