by TEI TEI

10/28/10 – Phase 1 & 2 are nearly complete. Punchlist is scheduled for 10/29/10 at 8am. All lights are installed, we want to change bulb color to cool white. We need price from Quality on isolation valve. QFP has been advised to replace the ceiling tiles in the main Administration area from the allowance monies.

09/27/10 – Next Const Mtg was rescheduled to Oct 6, 2010.

07/28/10 – Contracts have bee approved and signed. Awaiting first const mtg.

07/23/10 – Bids have been opened and approved. Pre Award meetings are complete. QCE is the electrical. Quality is the Fire Prot Contractor. Contracts have been written and approved by the Prosecutor dept. We are submitting a package back to the bldg dept to answer their concerns on permit issuance.

05/26/10 – Drawing stamped and signed. I will pick up the GC dwgs on Thursday and take to the permit office after Partner meeting. Budgets look good. Emergency lighting is an issue to design and may add more detail to for bidding. ITB was assigned 047-10. Bid set due June 4.

05/16/10 – Client review meeting brought up several issues that we have to fix before permitting. We will permit on 05/26.