01/02/08 – Final warranty info received 1/2/08, forwarded to MT

11/26/07 – Received As-Built drawings, forwarded to MT on 11/26/07.

10/01/07 – Awaiting closeout documents. Need As-Built drawings.

08/15/07 – CO #1 and Pay Application #3 sent to Michael Trabue.

07/27/07 – Construction is complete. Pay Application #2 sent to Michael Trabue.