11/19/19 – SOSS approved for Downtown Fire Rated Door Inspection RFP
11/19/19 – SOSS approved for Auxiliary Buildings Fire-rated Door Inventory
12/18/19 – Champlin sent Fire Rated Door Inspection Bid Documents draft to County
12/31/19 – Champlin began inventory at 250 Taft
01/03/20 – Champlin visited Juvenile Center
01/06/20 – Champlin completes rest of field visits
01/15/20 – Champlin received instructions from Tony Matre to combine both projects into one.
01/21/20 – Champlin receives access to archives for existing drawings of Auxiliary buildings
02/07/20 – Champlin expected to send bid documents to County

02/14/20 – Kru and Sam met with Bert, Tony, Jessica, and Rycca to discuss scope of work to be included in documents.  Champlin is waiting for service agreement draft from Bert.

11/20/20 – CA reached out to DHPace in Columbus for a unit price per door. No response after initial call. Reached out again last week and still no response. Looking for new contact to advise.