by TEI TEI

Project Lead: TEI

10/17/13 – Met Jackson at site for fieldwork.

10/25/13 – Vendor provided one for one replacement and rooftop model for bidding Base Bid and Alternate.

10/31/13 – Review drawings to be delivered to County for bidding as small project.

01/24/14 – Final bids came in during November. Waiting on Tony Matre to decide if we are moving forward with this project.

03/26/14 – Project may be on hold or done later. Ameresco work is currently being done at SPHQ.

0/6/20/14 – Project still on hold.

11/18/14 – Project rebid per Tony request. New Bids due Nov 26.

11/26/14 – Bid extended to Dec 3.

12/03/14 – New bids received. PHB was the apparent low bidder this year.

12/11/14 – New contracted drafted and sent to Tony with all the attachments for Prosecutor approval.

01/27/15 – Comments returned by Kerry, updated by TTE and sent back for approval. We are awaiting Pre Const Mtg. Peck has already sent submittals.

03/23/15 – Submittals reviewed. Equipment matches specs, when we kickoff this building.

04/14/15 – Held kickoff meeting for project.

04/28/15 – ThermalTech distributed meeting minutes from kickoff meeting. Submittals have already been approved.

05/25/15 – Contact PHB about status of project and equipment delivery.

05/26/15 – Submittals reviewed by TTC and forwarded to Tony, Mike and Paul. TTE requested an updated project schedule for use on this project.

06/24/15 – TTC checked in on progress with PHB

07/15/15 – Peck met Jackson on site to start laying out new work.

07/28/15 – TTC gave Bert the Energy Impact Study for this project.

08/26/15 – Peck scheduled to do startup on this project this week.

09/18/15 – TTC checked out unit install while on site. Project looks good. Owner can closed out the project as soon as closeout paperwork is received.

10/08/15 – MCB checked out unit while on site. Ready to archive.