by MCB MCB

02/26/20 – TEI authors and submits SOSS for project per HCFD request.  TEI receives PO and approved SOSS.  TEI and HCFD meet with CE Power for site investigation of existing conditions and remains of the disconnect switch that failed/caught fire.  CE power providing forensic’s report to TEI.

03/26/20 – CE Power has sent TEI forensics report.  TEI adding CE Power findings to TEI report to send to Hamilton county.

04/30/20 – TEI finalizes report draft to send to facilities for review.

05/27/20 – TEI has sent the draft of the report to facilities for review.  Will finalize upon receipt of comments.

06/23/20 – TEI has sent the draft of the report to facilities for review.  Will finalize upon receipt of comments.

07/29/20 – TEI has sent the draft of the report to facilities for review.  Will finalize upon receipt of comments.

08/21/20 – TEI has sent the draft of the report to facilities for review.  Will finalize upon receipt of comments