06/26/19 – TEI authors and submits SOSS for project.  Project pending approval of SOSS and PO.
07/24/19 – TEI receives approved SOSS and PO.  TEI to establish kickoff meeting with facilities and begin project.
08/27/19 – TEI to kick off this project once server room project is issued for bidding
09/25/19 – TEI is gathering data from the other projects for this report.  TEI to schedule meeting with HCFD for kick off meeting.
10/30/19  – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites.  The report is in process.
12/11/19  – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites.  The report is in process.
01/28/20 – TEI has report well in process and will submit draft upon completion.
02/26/20 – TEI has report near completion – pending one manufacturer (GE) responses.  Draft report to be submitted upon receipt and review of GE data.

03/26-20 – TEI to send to Facilities draft of report by 04/01/20.

04/30/20 – TEI send draft report to facilities for review.  TEI receives comments from facilities.  TEI modifying final report.