Hamilton County Facilities

Tony Projects

Admin – Chilled Water Pump Project
12/26/16 – Contract sent to Tony for approval on this project.
01/26/17 – DK says controls will be done my same team as controls project. Gleason has sent all required paperwork to Tony.
02/01/17 – Project kickoff to be schedule soon. CHW pump size will need to be coordinate with new chiller.
02/16/17 – Kicked off project with Tony, Bert and Gilbert. We are collecting chiller information now and rates for LCC equations. We will choose the chiller during the LCC and design around one chiller during design.
03/09/17 – Pump is on hold pending new size from LCC equations.
03/15/17 – Emailed Dave Gleason for update as work was supposed to begin last week and be done by end of March.
03/21/17 – Tony talked to Dave and they are starting next week with pipe fitting work. Steve Yockey is waiting on TEI to provide new pump size for selection work.
04/11/17 – ThermalTech provides new bypass size and flow for DK to install the bypass.
04/26/17 – TTC checked in with Dave Gleason on progress. Given the cooling season is here, they are going to have to work weekends and off time to fix these issues. The new bypass size was sent to DK but I do not know if it was installed yet.
05/02/17 – TTC checked up on project again with DK for progress.
05/25/17 – Debra stated they will replace the pumps and piping at the same time, later in June.
06/28/17 – Met Debra today on project update and they are getting employees finalized for this project understanding it will be weekend work at this point. Pumps are on order, VFD”s are a new change order, TTC to give to Tony, will be from new project on new PO for up charges.
07/18/17 – Met with Design time to redesign the piping for the new larger pumps on teh CT and CHLR job. Spoke with the manufacturer about sizes and head. Debra submitted new change order for entire project. TTC to estimate the entire job again for Bert with Construction budgets.
08/10/17 – We are waiting for the weather to break to start the pump replacement.
08/26/17 – Debra to drain system and install isolation valves Saturday but this was postponed due to material arrival issues. They will try the week after Labor Day.
09/25/17 – Isolation valves are installed and working. DK needs to insulated still. TTC met with DK and went over remainder of project on site. The scope of the original project lines up perfect with the chiller replacement project except this project does not need to install the bypass piping on the fifth floor. The CHW pumps will be installed by DK in this project, the VFD”s and submittals must be ordered ASAP, and the change orders have been sent for approval to DK and the County.
11/2/17 – Pump replacement work is schedule for December 2017. Debra is currently on site and working on this job.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – Only insulation remains to be completed. DK committed to wrapping this project up including controls by 4/30/18.
04/25/18 – Debra stated that all work on this project is complete including insulation. Final paperwork is being completed by DK now for all closeout paperwork. The final invoices are being delivered to Tony with a cover letter or remaining items.
08/02/18 – TTC inspected all final work including insulation and it looks really good. No additional punchlist items.

JC – Liebert Unit Replacement
11/14/16 – Final Addendum went out to bidders. Bid opening is schedule for Thursday.
12/07/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/28/17 – No updates from Tony on approved contract.
03/09/17 – Waiting for kickoff on this project.
03/15/17 – PO and Contracts are ready, TTC requested meeting times from contractors and owner.
03/21/17 – We are ready to have the kickoff meeting for this project.
04/26/16 – Submittals requested. Pre Const Mtg was held.
05/17/17 – Submittals approved. Equipment ordered.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Unit is on order and should arrive late July.
07/24/17 – Equipment should be here next week, DK people approved for access but some JCI people not approved yet.
08/10/17 – TTC met Debra and Andy on site to discuss break down and reassembly of the Liebert unit in the data room today. Debra not a fan of breaking down the unit, we are exploring the option of taking out the window and
08/30/17 – We are going to order the door for the replacement of the single door. TTC to work out allowance with Debra.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Piping is ran to the unit. The scaffolding is coming down this week. Insulation appears to be installed as well. Outdoor unit is set. The interior door work is underway. KFI ran into a frame issue today and is having the frame modified for a Wednesday install. Once we get the double doors installed the Liebert should be rolled into the place the rest of the job can commence.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.
04/25/18 – Project is complete and I believe final training is complete. Final payapps are being delivered to Tony on Thursday.
JC – Switchgear Replacement Project
01/08/16 – Met with Merkt on site to kickoff new AC unit in UPS room.
01/26/16 – Discussed scope of work with Tony and Joe over email today. Requested quote from Ray Weyman on Mitsubishi split at 4 tons for this room. This work may be a change to existing elevator work for cooling with Debra or owner will self-perform this work.
02/08/16 – The 4-ton unit only comes in a heat pump option but that heating can be locked out to provide cooling only. The 3-ton unit is a single wall unit with a single condensing unit. The 3.5 ton unit is ceiling cassette with a 3.5 ton condenser.
05/18/16 – Tony requested new SOSS for this work.
06/23/16 – ThermalTech was onsite performing fieldwork for equipment layout for about 3 hours today. We tracked down equipment locations for the Liebert and Mitsubishi Units and possible power sources for both.
07/18/16 – Phone conference today between Cannon, Merkt, Denton and Matre has decided to use an inline DX coil for HV-9 to cool this space similar to the work we are doing in the elevator room upstairs for additional cooling when the CHW plant is down. ThermalTech will modify the design.
07/20/16 – TTC on site for more fieldwork and duct measurements for new coil design.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/27/16 – We changed the design of the switchgear room AC to a coil and condenser unit and started requesting new cuts from Carrier. We are updating the plans now. The Data Room AC unit was changed for low supply and top return and we will try to collect the hot aisle air with a return duct above the data racks.
08/03/16 – Some progress made on design. Cad files received from Leibert this week, we are updating outdoor equipment.
08/25/16 – Design will be complete and ready for bidding in mid September for both phases.
09/01/16 – Review drawings due Sept 16.
09/23/16 – Project set to bid on 9/29/16. Prebid Oct 6, Bid opening Oct 20.
09/28/16 – Project is issued for bidding. Switchgear AC unit is the base bid. Liebert Unit and Medical Unit are Alternate bids.
11/10/16 – Contracts are written and sent to Tony.
12/09/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/21/17 – Submittals are in for approval. We are definitely having some trouble finding the medical valves but Peck is working with us to find them.
03/09/17 – TTC to finish submittals this week.
03/21/17 – Submittals are marked up and ready to go back to Debra.
05/17/17 – Submittals returned, equipment ordered, waiting for DK to get started.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Equipment is ordered and en-route. We have agreed to use a ceiling mounted cassette on this project. DK submitted a change order allowance usage for this work.
07/24/17 – Equipment should be here next week per Debra Kuempel.
08/10/17 – Coil is installed downstairs in UPS room. Medical unit is installed upstairs.
08/30/17 – Work is progressing well, Cassette is installed upstairs. Coil is installed downstairs, balance report is short on airflow from existing unit.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Debra reports that most work is complete. TTC checking on progress on the electric and controls portion of the job.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.

04/26/18 – Purchase order came out this week. ThermalTech agreed to perform the airflow readings for Debra and will share the results with the team. Then we will setup that conference call to discuss the results and proposed upgrades with the new motor.

Energy Manager
04/03/18 – TTC updated the Duke Proposed Rate increase in the Energy Outlook section and incorporated all of RWL notes into the Rev 2 file and created Rev 3 and sent to Ralph and Tony for approval.
04/04/18 – Rev 3 of the 2017 Energy Report is complete. The editable Word file was sent to Ralph for approval by Judi prior to submission to the BOCC.

04/26/18 – Ralph reported that the final report is in the editing stage and he will return as soon as Judi has markups.