Project Lead: THP
06/01/12 – THP submitted SOSS.
09/13/12 – County approves SOSS.
10/04/12 – THP County kick-off meeting complete. DD documents due early November and Final bid documents due mid-December with a budget. Bid period mid-February.
10/31/12 – THP working on DD documents.
01/15/13 – THP Issued DD documents for review.
02/08/13 – County returned project manual comment.
02/19/13 – THP and County had a design review meeting.
05/17/13 – THP issued 95% Review documents to the County.
06/27/13 – Project update. Due to weather sensitive work, if project approved work will not occur until next spring. Possible bid project late 2012.
10/31/13 – Project on hold.
01/30/14 – Project on hold.
04/24/14 – Project on hold.
06/26/14 – Project on hold.
07/31/14 – Project on hold.
08/27/14 – Project on hold.
09/25/14 – Overall project on hold.
01/29/15 – Overall project on hold.
02/26/15 – Overall project on hold.
03/26/15 – Overall project on hold
04/01/15 – THP requested to assess current roof condition and provide a summary report letter.
04/17/15 – THP published roof assessment letter with updated opinion of probable cost.