Hamilton County Facilities

Archived Projects

Archived Projects

Comm Center – BE Assessment (F041)

PM: Rycca Thacker / Ian Zellner, John Millar
03/06/26 – HC requested an assessment SOSS.
03/13/26 – THP provided an SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working on Assessment. Roof testing/thermal scans 4-6 weeks out from April request. Testing contingent on weather conditions.
06/16/26 – THP completed field survey and roof scans.
08/05/26 – THP published the final report.
08/27/26 – Put into Archibus. THP has full restoration and partial, agreed to enter full cost and in notes put reduced scope.

Comm Center – BE Assessment (F041) Read More »

Crime Lab – Electrical Coordination Study

PM = Rycca Thacker, Mike Barth

04/29/26 – HCFD requests DEG to visit the site to discuss issues with exterior lighting circuitry. DEG to submit SOSS for partial electrical coordination study for affected circuits.
06/23/26 – DEG receives PO and signed SOSS. Electrical Study commences.
07/29/26 – DEG conducts site visit to document all existing breaker model and serial numbers to perform the analysis. Project Analysis being modeled in easy power program.
08/26/26 – Coordination study and report draft sent to HCFD for review.
09/23/26 – trades electricians to adjust settings. Project complete.
10/28/26 – Project complete. Can this be archived.
10/29/26 – TTC archived.

Crime Lab – Electrical Coordination Study Read More »

JC – Kitchen and Laundry Water Heater Upgrade

PM: Matt Butz, Terry Cannon
02/12/26 – DEG kicking project off and setting up fieldwork.
02/25/26 – We’ve confirmed the new heaters are the high temperature laundry and kitchen PK heaters. The SOSS is submitted and DEG is beginning preliminary engineering.
03/25/26 – SOSS submitted, project setup.
04/29/26 – Initial fieldwork started, drawing setup underway. Pat Bemmes will be assisting with this project.
05/27/26 – Drawings are setup, equipment submittals and cost have been requested from vendors.
06/25/26 – Project put on hold. Send final DEG invoice.

JC – Kitchen and Laundry Water Heater Upgrade Read More »

SPHQ – AHU-3 Replacement

PM: Matt Butz, Terry Cannon
02/12/26 – Kickoff meeting being scheduled with HamCo.
02/25/26 – The SOSS has been submitted. Barrett meet Ian on site and review existing conditions. This unit is only five years old, do we really want to replace it.
03/25/26 – Waiting on SOSS and kickoff meeting to determine final scope.
04/26/26 – Internal meeting on project progress. We will scheduled next meeting with Ian after 525 RECX gets underway.
05/27/26 – On hold wafting on direction from County on how to proceed. AHU already replaced five years ago.
06/25/26 – Project put on hold, send final DEG invoice.

SPHQ – AHU-3 Replacement Read More »

111 – Antenna Power Upgrade

PM: Rycca, Barth
12/05/25 – Met onsite to gather SOSS data for this project. DEG to submit SOSS for this work.
01/28/26 – DEG receives SOSS and PO. Working to schedule a progress meeting with RT availability.
02/25/26 – DEG submits to the City of Springdale for permit for work. Install pending permit approval.
03/25/26 – DEG receives permits from Springdale. HCFD schedules install with MobilComm.
04/29/26 – Work complete. Closeout?

111 – Antenna Power Upgrade Read More »

CH – Stone Stair Assessment (F033)

PM: Rycca Thacker, John Millar
09/03/25 – County asked THP to review stair condition at Courthouse stairs.
10/03/25 – THP submitted SOSS.
10/17/25 – County approved SOSS.
12/11/25 – THP plans to walk the steps next Monday and provide a report by 12/15/2025.
01/28/26 – THP is currently reviewing existing conditions and discussing internally.
02/17/26 – THP issued a draft report.
02/23/26 – THP issued final report.
02/25/26 – THP updated Archibus project request.
03/26/26 – OK to Archive.

CH – Stone Stair Assessment (F033) Read More »

Crime Lab – Leak Investigation (F032)

PM: Rycca Thacker, John Millar
08/28/25 – County asked THP to review water infiltration at the coroner building.
09/05/25 – THP completed an initial site visit to investigate the conditions.
02/25/26 – THP had follow meetings and discussion with HC. THP published an email with summary of potential leak areas and an opinion /of probable costs.
04/03/26 – Based on THP recommendations, County directed THP to complete water tests of the suspect areas.
04/09/26 – THP and HC staff completed water testing at the louvers and screen wall. Testing found multiple leaks in the screen wall.
06/25/26 – Project Archived.

Crime Lab – Leak Investigation (F032) Read More »

Alms & Doepke – City Knock Down (F028)

PM: Rycca Thacker, John Millar
05/06/25 – County approved SOSS.
05/23/25 – County and THP had a kick off meeting.
08/28/25 – THP anticipates sending bid documents to contractors on 8/29/25.
09/02/25 – THP issued bid documents to American Façade Restoration, Buckeye Concrete Restoration, Hardig Industrial Services, and ZSR Contracting and Restoration. Kestner was unresponsive.
09/09/25 – Site prebid meeting occurred.
09/17/25 – Bids were received from three contractors. American Façade Restoration was the low bidder.
09/19/25 – THP reviewed the proposal with American Façade Restoration.
09/22/25 – THP published the a recommendation for American Façade Restoration to complete the work for the County to review.
09/24/25 – County requested additional bidders from the Bold list be invited to bid the project.
09/25/25 – THP sent three additional requests out to BSBE and MBE firms.
10/03/25 – THP received one proposal from LRT that was $15,000 over the low bidder.
10/15/25 – County issued a PO for AFR to complete the work.
10/29/25 – AFR is working through background checks. AFR is proposing to complete the work 11/10 to 11/14. Work is weather dependent and second shift.
12/11/25- THP has completed the survey at the building and is working on providing a City report regarding the observation by next week.
01/18/26 – The report has been approved by HC and THP submitted the report to the city.
04/30/26 – OK to archive this project.

Alms & Doepke – City Knock Down (F028) Read More »

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

230 – Summer Boiler Replacement

PM: Tony Matre, Terry Cannon
07/31/25 – SOSS approved. ThermalTech is conducting fieldwork to see if we can fit a boiler into the elevator and down to the in a size matching the KN boiler 2000 MBH. We did confirm that the boilers intended to be used on the Ameresco will not fit into the elevator, but they are 2500 MBH.
08/20/25- Final review drawings ready to review. TTC will send to County for review.
08/25/25 – Boiler selection is waffling, not sure where guys are going to fit a boiler in the elevator and down to the basement. We decided to have a base bid boiler and an Alternate boiler that matched future boilers.
09/24/25 – Review will be sent to Tony Matre for his review today.
10/29/25 – TTC preliminarily setup prebid meeting but did not get confirmation from bidders except one bidder (Triton) who showed up. TTC to reschedule.
11/14/25 – Prebid meeting with four vendors.
11/26/25 – Bids received, tabulated and sent to County. All bids were overbudget.
12/12/25 – TTC repackaged drawings and sent to DK for State Term pricing.
01/25/26 – County deciding if they want to award this project via State Term to Emcor and Debra Kuempel.  It does sound like it is going that way.
02/25/26 – No update on moving forward on this project yet.
03/25/26 – No update, still awaiting green light from County to move forward with state term work.
04/26/26 – DEG and Ameresco working on new boiler plant, this project can be archived.

230 – Summer Boiler Replacement Read More »

TPC – 7th Floor New Sink

PM: Megan, Terry Cannon
05/14/25 – Field trip to site with Rycca.
07/28/25 – Owner review set sent to County.
08/20/25 – Option 1 & 2 sent to owner for review with cost estimates.
08/28/25 – We received prices for SS pans and will update the cost estimate and send back with updates today.
09/24/25 – Project is also on 2026 Project Cost Estimates, we will use same numbers for the estimate.
10/29/25 – Project is updated in Archibus 26-ADM-0138-2485.
12/12/25 – TTC needs to revisit site with Rycca for new scope.
01/25/26 – Ryan and Sam to meeting with Rycca for kickoff meeting – waiting to here back about when this will be. We do need to draft an SOSS for this work and bid it out Small Project.
02/25/26 – Waiting to send SOSS, latest news was that this may be included in a bigger floor renovation?
03/25/26 – Questions out about final scope and expanded floor plan. Revised SOSS not submitted yet.
04/29/26 – Scope questions answered, DEG owes Champlin revised SOSS for final floor plan.
05/27/26 – Project On hold.
06/25/26 – Project on hold.

TPC – 7th Floor New Sink Read More »

230 – Multipurpose Room Renovation, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Mother’s Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with Mother’s Room.
01/29/26 – Need meeting with COA/Probate/HCFD to review scope.

230 – Multipurpose Room Renovation, Prosecutor’s Office Read More »

230 – Mother’s Room Addition, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Training Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with MultiPurpose/Training Room.

230 – Mother’s Room Addition, Prosecutor’s Office Read More »

SPHQ – Parking Lot Repave (F025)

PM: John Nester, Paul Bellman

04/01/25 – County requested SOSS to repaving of the Patrol HQ Parking Lot.
04/02/25 – THP completed a preliminary walk of the site.
04/18/25 – THP coordinated consultant proposals from Kleingers and Terracon.
04/24/25 – THP to publish SOSS for review.
05/07/25 – SOSS approved.
05/19/25 – Design kick off meeting complete.
05/29/25 – Civil survey and underground detective work complete.
06/25/25 – Terracon scheduled for underground exploration. THP coordinating with HC.
07/16/25 – Terracon completed borings and sent Draft report.
08/15/25 – Terracon sent final boring report.
08/28/25 – Meeting scheduled with THP, Kleingers, and Terracon to review boring report to finalize plans. Told Rycca THP can have this out late September.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
12/11/25 – Project on hold till further notice.

SPHQ – Parking Lot Repave (F025) Read More »

230 – Exterior Signage Feasibility Study

PM: John Nester, Eryn Thamann
03/26/25 – SOSS provided and pending approved PO.
04/24/25 – PO provided. HCFD to schedule kick-off mtg.
05/28/25 – Design kick-off meeting held with the Court/Court Admin/HCFD. Elevar to provide timeline for first round of design.
06/26/25 – Elevar to provide zoning code info to HCFD and not signage design options yet.
07/31/05 – Draft code study sent to HCFD for review.
08/28/25 – Renderings provided to HC on 08/25.
09/25/25 – Elevar needs final design and digital seals to proceed with Small Projects bid.
10/30/25 – Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Archive?

230 – Exterior Signage Feasibility Study Read More »

Record Center – Animal Shelter Renovation

PM: John Nester, Sam Hofmann, Terry Cannon

02/27/25 – SOSS returned. Kickoff to be scheduled in near future.
03/25/25 – Preliminary HVAC and plumbing calculations started.
03/27/25 – Kick off meeting held. SD in progress.
04/24/25 – Follow up programing meeting held. SPoA is working on plans to be provided in next couple of weeks.
05/29/25 – Programming meetings in progress.
06/26/25 – Programming meetings still in progress. Finalizing schematic plan with SPoA.
07/24/25 – TTE sent SD cost for MEP work to Champlin for use on this project.
07/31/25 – Schematic design plan finalized. Site and DD developing.
08/28/25 – Last schematic meeting to be scheduled. County needs revised estimate for next steps. Keep Rycca looped in. TTE cost up near $2M so far.
09/25/25 – Estimate provided to county based on finalized SD Plans. County to determine feasibility of moving forward.
10/30/25 – Final schematic design meeting held to determine next steps with 7-9 million dollar budget gap. County to discuss with Cares to determine the minimum amount of renovation they need to use record center.
12/11/25 – Murphy met with Caroline to discuss scope and possible reductions. County to provide direction on funding of the project. No movement until budget is set.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – No Update. OK to Archive.

Record Center – Animal Shelter Renovation Read More »

General Structural Services (F019)

PM: Rycca Thacker, John Millar/Paul Bellman
04/24/25 – THP completed an initial analysis of the Hillcrest storage shed truss/decking for review by the County. Preliminary findings for published via email.
07/30/25 – THP was requested to review Justice Center parking configuration and walked the site with John and Tony.
08/14/25 – THP published two Justice Center parking options for review by the County.
08/28/25 – THP attending monthly meetings, updating website and coordinating structural questions.
09/25/25 – THP attending monthly meetings, updating website and coordinating structural questions.
10/24/25 – THP submitted updated General Service SOSS.
10/29/25 – THP attending monthly meetings, updating website and coordinating structural questions.

General Structural Services (F019) Read More »

1916 – Building Assessment

PM: Rycca Thacker, Eryn Thamann
12/12/24 – Project created for tracking.
01/29/25 – Draft copy sent out. Elevar finalizing photo and final cost portions now.
02/25/25 – Final report provided after requested edits.
03/26/05 – Requested revisions have been made. Waiting on a few last elevator assessment items from Wes.
04/24/25 – Elevator evaluated. Final report provided to RT along with bound copies as requested.
05/28/25 – Final report provided in April.
05/29/25 – Archived.

1916 – Building Assessment Read More »

Hillcrest – Campus Repairs Phase 2

PM: Megan, Sam, Hofmann, Terry Cannon

01/27/25 – Create new project for tracking.
02/26/25 – ThermalTech has preliminary started creating the second phase floor plans for MEP.
02/27/25- Because this is tied to Federal Grant money, Phase 2 may not proceed and potentially fall back to Trades to do the work hodgepodge in the future. CCF Grant Funding in summer 2025 at state level and make give us some indication of what we are doing future.
03/25/25 – Project on hold until further notice.
04/23/25 – Project on hold.
05/28/25 – Project on hold.
06/25/25 – Project on hold.
07/30/25 – Project on hold.
08/28/25 – Project on hold.
09/24/25 – Project on hold.
10/30/25 – Project on hold. High level cost was sent to Rycca for grant purposes include the updated cost for design partners. updated Kitchen cost also sent to County.
12/11/25 – No update.
12/12/25 – Some items in Phase 1 being moved to Phase 2 for example school sink solids interceptor, repairs in Maple cottage, dining rec RCP.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – Grant is pending. Scope will be reduced to fit budget of grant. SOSS incoming to right size fee for reduced scope.
05/28/26 – No Update.
06/25/26 – 1.5 million grant awarded. Phase 2 scope meeting held. County to determine budget and design partners to provide updated SOSSs.
07/30/26 – No Update. Remove from list.

Hillcrest – Campus Repairs Phase 2 Read More »

A&D – Water Heater Draft Study

PMs: Tony Matre, Terry Cannon

01/27/25 – Wireless space pressure sensors installed 1/24. Initial pressure readings indicate the water heater room is slightly negative (0-0.025 in WG) compared to both outside and the elevator machine room. The observed airflow showed consistent flow from the elevator machine room into the water heater room and from the water heater room to outside, suggesting the pressure would be elevator machine room > water heater room > outside. The observed draft on the water heater was a slight backdraft from the flue into the water heater room. The thermal camera was used to look for temperature gradients in the flue which could indicate a clog, but none were observed. ThermalTech is continuing to observe pressure readings and look for irregularities.
02/26/25 – Wireless equipment has been installed and we are monitoring the room. We have had one incident where the air seemed to be moving into the elevator room. TTC discussed with Glen cover all transfer openings and continuing to monitor for another 30 days.
03/13/25 – Covers were placed on the VAV duct and the transfer grill between the mechanical room and elevator to isolate the room from draft influences. Another test was conducted when there was little draft by opening the door to provide combustion air, but this did not fix the issue either.
03/25/25 – Draft still an issue. ThermalTech camera the flues and found them to be clear.
TTE brought in a Enervex for a third party review of the installation. They suggested extending the flues another 6ft each and thought the additional elbows added below the heaters might be a problem, they are running flue calcs for us to review.
04/23/25 – Project recommendations sent to Tony and Glenn and some additional conversation was had, but we have not been given direction to where to go next. We recommend new roof penetration and longer flue pipes to eliminate the issues.
05/28/25 – Project on hold.
06/25/25 – Waiting on County direction for next steps.
07/30/25 – Prices came back too high and too much scope. Barrett reached out to DK to realign cost and scope.
08/28/25 – Prices updated and given to Tony and Glen for next steps.
09/24/25 – Archived.

A&D – Water Heater Draft Study Read More »

Records Center – Showers, Washers, Dryers

PM: John Nester, Terry Cannon

12/12/24 – Plumbing drawings for dog washing shower area submitted and construction began last Friday.
01/27/25 – Triton has secured permit and is currently installing the dog showers in the facility. The trench drain has been cut, they didn’t like the cover, we are working getting a grated cover instead.
01/28/25 – Field visit reviewed existing conditions. TTC will send some questions to Triton about the install as a follow-up. The trench drain cover has been replaced and is currently curing.
02/26/25 – Showers and trench drain installed. Washer and dryer work is underway as well.
02/27/25 – Ready to Archive. Move all washer and dryer time to new Records Center Animal Shelter.
03/25/25 – The showers, washers and dryers are installed and being used.
04/23/25 – Space is in use this phase can be archived. New work will be picked up on the Records Center Animal Shelter project.
05/28/25 – Archive this project.

Records Center – Showers, Washers, Dryers Read More »

Colerain – Animal Shelter Wood Canopy (F020)

PM: John Nester, John Millar
10/21/24 – HC reached out to THP asking for repair of the Animal Shelter Wood Canopy.
10/31/24 – THP reviewed internal past documents and County email. THP to meet with County to discuss next steps.
12/11/24 – THP working on repair design.
12/16/24 – THP surveyed the site and met with County personnel. Shoring configuration was discussed and direction was given to install preliminary shoring.
12/17/24 – THP sent shoring detail for review.
12/19/24 – HC installed shoring and sent photos of sample shores. Shoring detailing was confirmed.

Colerain – Animal Shelter Wood Canopy (F020) Read More »

A&D – Elevator System PM Agreement

PM Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre met to establish project schedule. The project in process.
02/26/25 – No updates this month
03/26/25 – No Updates this month.
04/23/25 – Project manual near completed. XBE paperwork to be submitted for approval then ITB will be issued.
05/28/25 – No Updates

A&D – Elevator System PM Agreement Read More »

230/800 – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Tony meet and establish project schedule. Project in progress.
02/26/25 – No updates this month
04/23/25 – No updates this month
05/28/25 – No Updates
09/24/25 – DEG and AKM discuss that this goes out to bid mid October. Also discuss 1 year contract with optional 1 year renewals pending the elevator replacement projects.
10/29/25 – Project to be sent to purchasing on 10/31/25 for bidding.
12/10/25 – Prebid occurred on snow event day. A send prebid occurred on 12/08/25 for the bidders that could not attend during snow event. Bids to open on 12/29/25.
01/28/26 – Tony M and Bonita drafted contract and sent to Prosecutor.

230/800 – Elevator System PM Agreement Read More »

TPC – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to develop project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – No updates this month.
04/23/25 – No updates this month.
05/28/25 – No updates

TPC – Elevator System PM Agreement Read More »

All Buildings – Generator Systems Inspections and Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – TEI visits all building sites that are new to inventory/coming online this spring/summer. TEI submits DEI paperwork. As soon as approved by DEI – ITB will be issued.
04/23/25 – TEI issues project for bidding. Prebid meeting was on 04/21/25. In bidding phase.
05/28/25 – Bids received. (2) bidders. Project in contract phase.
06/25/25 – Project in contract phase.

All Buildings – Generator Systems Inspections and Testing Read More »

All Buildings – Fire Alarm System Inspections & Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish schedule. Project in progress.
02/26/25 – No updates this month. AKM wants bid out in April ’25
03/26/25 – No updates this month. Work to occur in April 2025.
04/23/25 – Nick (TEI) developing and updating the data sheets for the buildings with newer systems. XBE paperwork in works and ITB to be issued.
05/28/25 – No updates
06/25/25 – No Updates
08/27/25 – DEG going to issue bid package first week of September. Proposed (AKM approved) prebid dates are 9/15 and 9/16.
09/24/25 – DEG issues for bidding. JCI, Siemens and SA Communale indicate interest in project. Prebid dates are 09/23 and 09/24, no bidders attended the prebid walk thrus. bid openings 10/22.
10/29/25 – SA Communale Only bidder. AKM working on Contract.
12/10/25 – Project in contract phase.

All Buildings – Fire Alarm System Inspections & Testing Read More »

2020 – WiFi System Study

PM = John Nester – Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO.
01/29/25 – TEI and HCFD to conduct study walk thru of building in next 2 weeks.
02/26/25 – TEI requests time with HCFD to perform study walk thru
03/26/25 – TEI and HCFD walk the building to locate/document the existing WiFi system devices. Report is in progress.
04/23/25 – TEI to have draft report for review by HCFD/2020 staff by mid May.
05/28/25 – TEI has a draft review meeting with the HCFD/2020 staff. TEI finalizing a few modifications to the draft and will distribute to team for review/comments.
08/27/25 – DEG sends final report with HCJC comments included.
10/29/25 – DEG addresses C Walsh questions via email
12/10/25 – No updates this month

2020 – WiFi System Study Read More »

Colerain – Animal Shelter Boiler Replacement

PM: Tony Matre, Terry Cannon

09/26/24 – After SD and pricing efforts, we have decided to bid this project via Small Project bid with one for one like boiler and no recirculation pump replacements in the Base Bid.
10/30/24 – Drawing are modified and ready for bidding. NKY will be but no word back from DK and Geiler on their willingness to give us a price for this work.
12/12/24 – No updates since last meeting. BW said to go ahead and get three prices for the boiler replacement but they are not moving on doing the work this year. One price received so far.
01/28/25 – No updates.
02/26/25 – No updates.
03/25/25 – No updates.
03/26/25 – Tony confirmed this project on hold. No work for TEI at this time.
04/23/25 – Project on hold.
05/28/25 – Archive until further notice.

Colerain – Animal Shelter Boiler Replacement Read More »

All Buildings – Fire Sprinkler Inspection & Testing 2025

PM: Tony Matre, Terry Cannon

09/26/24 – SOSS Requested.
10/30/24 – SOSS submitted. Preliminary project setup has begun. TTE needs to add three buildings to the bid this time around, 111, 525, 4210 Dane, Crime Lab and Coroners Office.
12/12/24 – Approved SOSS and PO not received yet.
01/28/25 – PO received. Preliminary specs assembled by Barrett. We need to scheduled fieldwork to confirm quantities. We heard the first deadline for draft review is end of February.
02/26/25 – Limited updates, we will be working on this one in March.
03/25/25 – No updates. We still plan on bidding this job by end of April.
04/23/25 – Fieldwork is completed. New buildings are added, old buildings are removed. Specs have been updated for 2025 Code references. The Project manual is ready for Tony Matre review.
05/28/25 – TTC compiling proposed bid cost to request the ITB number for this project. Trying to scheduled a two day prebid for this project. Bid will be in June.
06/25/25 – Prebid meetings scheduled for July 9,10.
07/21/25 – Addendum #1 sent to bidders.
08/28/25 – Bids opened and awardable. SA Comunale had only openable bid. Next steps by County.
09/24/25 – Contract being drafted. We answered some questions about the give year testing.
10/29/25 – Archive.

All Buildings – Fire Sprinkler Inspection & Testing 2025 Read More »

JC – Polished Concrete – Phase 1

PM Jesse Estes, Sam Hofmann

09/26/24 – Project to go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project went back out to bid and is opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract in progress.
03/27/25 – Kick-off scheduled for 4/2.
04/24/25 – Kick-off held. Submittals received. Mobilization to be scheduled.
05/29/25 – No update.
06/26/25 – No update.
07/31/25 – No update.
08/28/25 – Waiting on background checks to clear to begin.
09/25/25 – Concrete grinder sub walked out on project. Alpha is searching for replacement.
10/30/25 – Alpha found replacement grinder sub. Alpha discovered that all furniture on the 5th floor of the north building has been tack welded to the bolts. all furniture in the day space area will be removed and re anchored. All cell furniture will be grinded around as best as possible.
12/11/25 – Pods are complete. Alpha to begin central hallway.
01/28/26 – Scope Complete. Waiting on closeouts.
02/26/26 – Closeouts received and missing items requested.
03/26/26 – Items still outstanding.
04/30/26 – Items returned. Hard copies outstanding.
05/28/26 – No Update.
07/30/26 – Closeouts delivered to County.

JC – Polished Concrete – Phase 1 Read More »

230 – Façade Repairs (F016)

PM: Matt Butz, Fateme Shahiyan

08/29/24 – County request THP rebid Alternate Façade repair package from SOSS F003. SOSS Hamilton County.
09/23/24 – THP published review drawing to County.
09/23/24 – County provided review comments to THP.
09/26/24 – Final bid to be released to purchasing with Advertise to bid scheduled for 9/30/24. Bid opening scheduled for 10/30/24.
10/16/24 – THP issued Addendum No. 1 – (prebid minutes and updated prevailing wages).
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received.
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received and BCR was the lowest bid.
11/05/24 – THP had a Bid Review with BCR
11/14/24 – THP sent the bid summery and recommendation letter for BCR to Hamilton County.
01/16/25 – Preconstruction meeting completed.
01/29/25 – Progress meeting completed.
01/30/25 – Project status – BCR has rigged and complete the first knock down survey of the north elevation. Work will progress north to west to south.
02/21/25 – Crew moved to the west elevation to do the knock down and have the spots ready to patch when temperature gets better in the next week.
02/24/25 – BCR send out Pay App No.1 for THP review and THP approved that.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/26/25 – BCR start installing the swing stage on roof for the north return wall of the building.
03/31/25 – BCR completed the work and sounded the north return wall. No major sports or damage.
04/04/25 – BCR submitted pay app No.2 and was approved by THP. BCR needs to provide the closeout documents.
05/27/25 – BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/10/25 – BCR has provided all closeout documents, which have been approved by THP. BCR is in the process of sending the notebooks and USB drive containing the documents to the County. Once that is completed, THP will send the signed final pay application to HC.
07/30/25 – Project status: All closeout documents approved. Waiting on project notebooks.
08/26/25 – BCR planning on complete the closeout documents and send it to the county by end of the next week along with the TPC project.
09/15/25 – BCR dropped off the closeouts documents to HC/Matt Butzz. However, the electronic documents, notarized warranties and 2 payrolls for the project were missing. BCR is planning to provide the documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.

230 – Façade Repairs (F016) Read More »

2025 Structural Estimates CIP Resubmittal (F010)

PM: John Nester, John Millar

06/11/24 – THP HC requested SOSS for project estimates broken down by New, Resubmittal and CIP Resubmittal.
06/25/24 – Champlin published draft project lead list.
07/15/24 – Thermal Tech published final edit.
08/28/24 – THP published SOSS.
08/29/24 – THP working on estimates.
09/26/24 – THP finalizing estimates.
12/11/24 – THP completed structural project estimates.

2025 Structural Estimates CIP Resubmittal (F010) Read More »

Colerain – Animal Shelter Electrical Investigation

PM = John Nester, Mike Barth
08/28/24 – ThermalTech submits SOSS for approval.
09/25/24 – TEI receives signed SOSS and PO. TEI contacts Bldg Mgr to schedule site eval (tentatively 9/30 or 10/1).
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – TEI develops drawings for County review.
02/26/25 – TEI develops permit documents and HCFD solicits quote from Glenwood (emergency on call electrician), Glenwood submits drawings for permit.
03/26/25 – Plan review complete and approved. Glenwood pulls electrical permit and to schedule install.
04/23/25 – Glenwood proceeding with the removal of the raceway and installation of the new conduit system. HCFD to notify TEI when complete and a punchlist visit will be conducted.
05/28/25 – Project completion pending punchlist.
06/25/25 – HCFD and TEI complete punchlist. No items identified on punchlist. Project complete.

Colerain – Animal Shelter Electrical Investigation Read More »

CH – Re-Drape and Blinds

PM: Eryn Thamann, John Nester, Jesse Estes
08/27/24 – SOSS approved. JN to send new drape/blind info for review prior to scheduling site visit.
09/24/24 – JN to send info and meeting invite to review mock up.
10/30/24 – Elevar met with Court Admin to review mockups. Drawings started for SD.
12/09/24 – SD review meeting with HCFD/Court Admin scheduled for next week.
01/29/25 – Met with Court Admin and revised drawings based on meeting. SD review package is nearly ready for HCFD final review.
02/26/25 – Drawing package submitted to HCFD for final review.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
06/26/25 – No update.
07/31/05 – Elevar to research historic requirements for elevations.
08/28/25 – No historic restrictions on interior window treatments and confirmation sent to HC.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Archive?

CH – Re-Drape and Blinds Read More »

2020 – Sewer Deduct Meter

PM: Tony Matre, Terry Cannon
05/28/24 – Cooling tower makeup water reviewed and approved by GCWW and should be on bill next billing cycle.
06/27/24 – Irrigation sewer deduct ready to review by County. It’s ready to send to GCWW.
07/24/24 – Second deduct meter sent to County for review. TTC followed up by email.
08/28/24 – Received Tony signatures on final paperwork, ready for submission to GCWW.
09/24/24 – Second application has been given to GCWW and MSD, they confirm they have it but it has not been reviewed or processed yet.
10/30/24 – Additional data requested and sent last week to MSD.
12/12/24 – MSD and GCWW have all the data they need, we are waiting on their approved and meter review. The first meter has been on the bills since June, and we are getting a deduct for it. Meter number S03787, so far, they have saved a little over $1,000 in sewer charges in the first few months with the meter online.
01/02/25 – We have the meter and the transmitter has been located. We are moving towards installation in the near future.
01/27/25 – HC has installed the meter and transmitter. ThermalTech is coordinating the final inspection with MSD.
02/26/25 – Meter has been installed and approved. We will check water bills to see when it shows up on the GCWW bill.
03/25/25 – Sewer deduct meter not on water bill yet.
04/23/25 – March water bill has both sewer deduct meters logged on the bill but the irrigation meter has no usage usage yet. This project is ready to archive.
05/28/25 – Archived.

2020 – Sewer Deduct Meter Read More »

230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003)

PM: John Nester, Fateme Shahiyan

04/26/24 – THP provided SOSS Hamilton County.
05/09/24 – County approved SOSS.
05/24/24 – THP provided review documents.
05/28/24 – County provided comments to review documents.
05/31/24 – THP provided Economic inclusion work sheet.
06/04/24 – Economic inclusion package returned to THP.
06/07/24 – THP issued bid documents.
06/20/24 – Prebid meeting occurred.
06/21/24 – Addendum no. 1 issued.
06/26/24 – Bid opening scheduled for July 23, 2024.
07/23/24 – The County received one bid from BCR. Base Bid was 8% over the project opinion of probable cost.
07/24/24 – Department of Economic Inclusion noted the bid was responsive.
07/25/24 – THP and the County to review the bid.
08/15/24 – THP published bid summary letter, recommending BCR.
09/26/24 – Earlier, County sent contract to BCR for execution.
10/04/24 – Contract executed and published.
10/15/24 – Preconstruction meeting occurred.
10/21/24 – County published rooftop safety tie inspection report.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
11/08/24 – BCR published the SOV for review by THP.
11/19/24 – BCR published their schedule for the project
12/04/24 – BCR sent the Pay App No.1 to THP
12/10/24 – BCR Resubmit the Change order No.1
12/10/24 – BCR sent revised Pay App No.1 to THP and THP approved it.
12/10/24 – BCR completed about 30% of the work including sounding and opening up the lintel areas on the fifth floor and providing temporary flashing over the top of the ledge angle.
01/30/25 – Project status – BCR completing sounding, concrete and masonry repairs on West Elevation of Todd Portune Center. Remaining work is corner of south elevation of the TPC. Due to low temperatures crews moved to the 230 WHT building to complete knock down survey work. Crews will return after work at 230 WHT is complete.
02/24/25 – Project is still on hold and crew are still working on 230 WHT.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/25/25 – THP send the pay app No.4 from BCR, to HC for the final review.
04/23/25 – Project is completed and BCR needs to provide closeout documents.
05/27/25- BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/25/25 – HC requested Change Order #3 (CO#3) for the emergency concrete repair on the north elevation of the Portune Center. BCR has provided CO#3 to HC, and HC is currently working to get it approved. BCR is planning to send the supporting documentation, including the cost breakdown with any applicable markups, to THP and HC by the end of this week.
07/01/25 – Change order #3 approved.
07/14/25 – BCR started work.
07/24/25 – THP visited the site and reviewed the work. Field report published.
07/25/25 – BCR finished knock down work.
08/26/25- BCR provided the last pay app for the emergency repair to THP for review. BCR planning on complete the closeout documents and send it to the county by end of the next week.
09/15/25- BCR dropped off the closeout documents to HC/Matt Butz. The electronic documents, notarized warranties were missing. BCR planning to provide all documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.
02/26/26 – Ready to archive.

230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003) Read More »

TPC – Auditors Breakroom Renovation

PM – John Nester, Sam Hofmann

05/30/24 – Kickoff meeting held. Several options are ready for review. Meeting to be scheduled for mid June.
06/27/24 – Meeting held with Paula to go through options. More direction given. A revised plan is in progress.
07/25/24 – Updated options have been sent to Paula. Waiting on her response to finalize plans. Estimate complete and submitted.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update. OK to Archive.

TPC – Auditors Breakroom Renovation Read More »

CH – JAX Door Control System PLC Study 2024

PM: John Nester, Mike Barth
05/29/24 – HCFD requests SOSS from TEI on 5/29/24.
06/26/24 – TEI submits SOSS.   Project pending SOSS approval and PO.
07/24/24 – TEI receives signed SOSS and PO. Study in development in conjunction with the JC Study.
08/28/24 – TEI meets with vendors to discuss industry trends and current offerings. Report in development.
09/25/24 – TEI finalizing report to send to HCFD for review.
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – HCFD and TEI meet with HCSO to review draft report. Final report to be submitted.
01/29/25 – Final report to be submitted with the JC report. JC report pending 1 item.
02/26/25 – TEI sends final report. HCFD sends additional final comments. TEI to incorporate and resubmit final report.
04/23/25 – TEI receives budgetary numbers from suppliers for additional features. TEI finalizing report and to submit draft.
05/28/25 – TEI Submits finalized reports to HCFD.
06/25/25 – TEI submits final report. HCFD requests cost for engineering (not an official SOSS at this time)
07/30/25 – DEG submits estimated SOSS cost to HCFD for review.
08/27/25 – No updates. County has all closeout documents. Ready to Archive. Put study into Archive Room.

CH – JAX Door Control System PLC Study 2024 Read More »

Crime Lab – Emergency Power System Upgrades 2024

PM: John Nester, Mike Barth
05/29/24 – TEI submits SOSS for approval.  Project pending PO and Signed SOSS.
06/26/24 – TEI receives approved SOSS and PO.  Documents in Process. Trades will be doing this work, TE to send final dwgs in for review. It will permitted through City of Blue Ash.
07/24/24 – TEI sends drawings to HCFD for review.
08/28/24 – TEI obtains permit from Blue Ash. TEI delivers permit and approved drawings to Keith Otis. Electricians state that material procurement stage – once materials arrive – will get installed.
09/25/24 – HamCo Trades Electricians to notify TEI when they are ready for inspections.
10/30/24 – TEI coordinates breaker types with trades. TEI to arrange inspections when notified by trades.
12/11/24 – Inspections pending call from trades re completed installation.
01/29/25 – Inspections pending call from trades re completed installation.
02/26/25 – Trades calls TEI and are ready for inspections. TEI to schedule with trades and Blue Ash.
09/24/25 – DEG and trades meet with blue ash and has approved inspection. Blue ash did not have records for final inspections for re-circuiting work. that inspection is scheduled for 10/01
10/29/25 – Revised documents in plan review stage.
12/10/25 – Permit applied for – pending approval for final inspection.
01/28/26 – DEG follow up with the City of Blue Ash.
02/25/26 – DEG and trades gets final inspections. All inspections and work passed with City of Blue Ash. Project complete.
02/26/26 – Give County as-built drawings and archive the project.

Crime Lab – Emergency Power System Upgrades 2024 Read More »

JC – PLC System Replacement SD & Estimate

PM: Matt Butz, Mike Barth
05/29/24 – TEI submits SOSS for approval.  Project pending PO and Signed SOSS.
06/26/24 – TEI receives signed SOSS and PO for project.   Study initiated and TEI is prepared to schedule meetings with the correct stake holders at the HCSO.
07/24/24 – TEI and HCFD discuss scheduling kick off meeting the week of 08/05.
08/28/24 – TEI meets with system suppliers to discuss latest industry trends and current offerings. Report is in development.
09/25/24 – TEI reviewing report and will send to HCFD for comments.
10/30/24 – TEI sends report to HCFD for review and comments.
12/11/24 – HCFD and TEI meet with HCSO to review report. HCSO asks if the Telecor cell intercom system is compatible with a new PLC. The PLC system will accommodate, TEI to investigate any potential modifications to the Telecor system that would be required and the potential cost implications, then the report will be finalized.
01/29/25 – TEI contacts ICS multiple times to get cost schedule implications. ICS not responding. Per Matt – we will issue the final report after 02/01/25 if no response from ICS by then.
02/26/25 – TEI submits final report to HCFD. HCFD sends additional comments to TEI to incorporate. TEI to resubmit upon completion of updates.
03/26/25 – TEI working with suppliers to get budget numbers for alternatives that were included.
04/23/25 – TEI receives budgetary numbers on 04/21/25 from suppliers. Final updates to be completed and returned to HCFD.
05/28/25 – TEI submits finalized reports to HCFD.
06/25/25 – Finalized reports are submitted. HCFD asks for an approx cost for engineering. Not an official SOSS at this point.
07/30/25 – DEG submits estimated design engineering costs to HCFD.
08/27/25 – No updates.
09/24/25 – No updates.
09/25/25 – OK to Archive.

JC – PLC System Replacement SD & Estimate Read More »

2025 Project Cost Estimates

PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.

2025 Project Cost Estimates Read More »

JC – CARE Pod Counseling Rooms

PM: Matt Butz, Sam Hofmann
04/25/24 – Project update at Partner Meeting
5/29/24 – Field verification confirmed. CDs in progress.
06/27/24 – Final floor plan given to Matt for confirmation of scope from sheriffs.
07/25/24 – Bid set in progress. scheduled for owner review on 8/9.
08/29/24 – Owner review set submitted. Project to be out to bid in next couple weeks.
09/26/24 – Project is out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Only bid received was non responsive. Project is back out to bid today.
12/12/24 – Bid opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract finalized. Kick off to be scheduled in near future.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals returned. Change order #1 processed. Mobilization to be scheduled.
05/29/25 – Project scheduled to begin 6/30.
06/26/25 – Start date delayed due to hollow metal frame manufacturer issue.
07/31/25 – All issues solved. Waiting on Alpha to schedule mobilization.
08/28/25 – Waiting on confirmation for glazing ship date. Alpha has reached out numerous times to McAndrews and has not gotten a firm response.
09/25/25 – Glazing will be delivered by end of november. Alpha will mobilize next week and install temporary glazing until the BR rated glazing comes in. Frames were delivered in one single piece which are too large to fit into any elevator. Frames will be cut in half in the field and welded back together once in place.
10/30/25 – Alpha’s mason walked out on the job. A couple masons reviewed the project before they settled on one. Electrical work is complete. Alpha is convinced that the mid November deadline will still be met.
12/11/25 – Punch walk through tenatively scheduled for week of 12/22. Mason work is almost complete.
01/28/26 – Back punch complete. Waiting on closeouts.
02/26/26 – Waiting on closeouts.
03/26/26 – Closeout items missing sent to Alpha. Awaiting final submission.
04/30/26 – Waiting on hard copies.
05/28/26 – No Update.
06/25/26 – Hard copies delivered. Final pay app approved.

JC – CARE Pod Counseling Rooms Read More »

A&D – Exterior Camera Upgrades 2024

PM: Matt Butz, Mike Barth
04/24/24 =  TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD to review.
07/24/2024 – HCFD moves location of NWS to 3rd floor data room. TEI updates the drawings.
08/28/24 – Project pending installation from DK.
10/30/24 – DK installs camera.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Finalizing binders.
06/25/25 – DK, DEG and HCFD to me re final closeout
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

A&D – Exterior Camera Upgrades 2024 Read More »

230 – Exterior Camera Upgrades 2024

PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for review from HCFD.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Project pending completion of installation from DK.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
06/25/25 – DK, DEG and HCFD to meet re final closeout.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

230 – Exterior Camera Upgrades 2024 Read More »

CH – Exterior Camera Upgrades 2024

PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to review scope of work and locations for equipment.   TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – project pending Historical society review of proposed mounting hardware and installation by DK.
12/11/24 – Historical Society approves installation. Project pending installation by DK.
01/29/25 – Project installation nearly complete. DK states that there is an Injector issue to resolve and project will be ready for punchlist.
02/26/25 – Project complete pending closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Project pending closeout.
04/23/25 – Project pending closeout docs from DK.
05/28/25 – Pending closeout documents.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

CH – Exterior Camera Upgrades 2024 Read More »

TPC – First Floor Lobby Cameras

PM: Matt Butz, Mike Barth
04/24/24 –  TEI receives signed SOSS ands PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Cameras installed last week. TEI and HCFD to schedule punchlist and review of camera views on the system.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

TPC – First Floor Lobby Cameras Read More »

CH – JAX Camera Upgrades

PM: Matt Butz, Mike Barth
04/24/24 – TEI receives approved SOSS and PO.  Kick off meeting occurred on site on 04/23/24.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small, projects bid. Prebid meeting occurred. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received on project (2 bids Glenwood and DK), DK apparent low bidder. TEI vets the bid from DK.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for pre-construction meeting. Anticipated construction to start 11/11/24
12/11/24 – DK states that the installation of the system in the JAX area is approx 90% complete.
02/26/25 – Project complete pending punchlist and closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Pending closeout.
04/23/25 – Project pending closeout.
05/28/25 – Project pending closeout.
07/31/25 – OK to Archive, send final bill.

CH – JAX Camera Upgrades Read More »

JFS – General Services

PM: Rycca Thacker, Terry Cannon

04/01/24 – JFS Category created to track JFS General Services work.
04/22/24 – 2024 SOSS submitted.
07/24/24 – SOSS not approved yet.
08/28/24 – No updates.
09/24/24 – No updates.
10/30/24 – No updates.
12/12/24 – ThermalTech working on draft issue in the penthouse with Glen on the Water Heaters.
01/28/25 – A&D draft troubleshooting is a JFS general services.
02/26/25 – OK to archive.

JFS – General Services Read More »

Barth Safety Prorgram

PM: Ted Graham, Mike Barth

03/28/24 –  Program started, poster created, training held, policies & procedures entered into the record for all to see 🙂


04/24/24 – Barth is still on the fritz, his doctor extended his convalescence another four weeks.  After that, they will probably just remove the foot and replace it with another hand so he can do three times as much work as he normally does.   One hand for CAD, one hand for the calculator one hand for a cell phone, his other foot will be used to kick the butt of all the coops at the office.


05/09/24 – Program membership has grown by 100%!  Welcome to the program Mr. Ted Graham!


06/18/24 –  Welcome to the program, Rycca!  This month’s safety topic is monitoring for Overexposure to UV Radiation.


07/24/24 – Hopefully no updates this month 🙂
08/28/24 – No updates to report.
09/24/24 – We have lost the tree, crying, grieving, and bemoaning has ensured.

Barth Safety Prorgram Read More »

CH – WiFi Upgrade

PM: John Nester, Mike Barth
02/29/24 – Bradley Bedacht contacted TE for new project. Project added to website.
03/27/24 – HamCo requests SOSS for Study of existing system and requested upgrades.
04/24/24 – TEI submits SOSS.  JN and TEI discuss scope and HCFD to confirm total scope.
05/29/24 – TEI and JN to confirm scope.
05/30/24 – This project returned to the Courts for their coverage. We can archive this job.

CH – WiFi Upgrade Read More »

Comm Center – EV Charging Project

PM: John Nester, Mike Barth
02/29/24 – Project created for tracking. MCB says we have all we need.
03/27/24 – Project docs to be sent to JN ASAP.
04/24/24 – BW and TEI review ODOT documents and submit what we can.  Balance of data required from tenant.
05/29/24 – Project pending data from tenant.
06/26/24 – Project pending data from tenant.
07/24/24 – Project pending data from tenant.
08/28/24 – TEI and HCFD develop a package to send to ODOT for review and commentary including bid documents, project manual and OPC. Package sent to ODOT on 08/28/24.
09/25/24 – Project pending ODOT approval.
10/30/24 – Pending ODOT approval
12/11/24 – No Updates from ODOT.
01/29/25 – No updates from ODOT.
02/26/25 – No Updates from ODOT.
04/23/25 – Received Stage 3 approval from ODOT. HCFD investigating funding gap from the grant and the updated costs. Then notify TEI on next steps.
05/28/25 – Next steps to be coordinated with HCFD.
06/25/25 – TEI sends updated opinion of probable cost to HCFD for county to discuss grant funding/cost differential.
07/30/25 – No Updates
10/29/25 – DEG receives email from HCFD that this project is cancelled. OK to Archive.

Comm Center – EV Charging Project Read More »

JC – Skywalk Roof Replacement & Exterior Repairs (F002)

PM: Bert Watts, John Millar

02/01/24 – Hamilton County requested an SOSS for roof replacement of Skywalk bridges.
02/29/24 – THP reviewed roof approach with Contractor and roofing manufacturers. THP working on proposal.
03/14/24 – THP issued DD review set of roof replacement with the Skywalk Exterior façade repair.
03/28/24 – THP working on bid package.
04/25/24 – Project combined with F077. THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
07/19/24 – THP issued Bid Documents to the County and Arc.
07/22/24 – Bid Documents Released on Bid Sync.
07/25/24 – Prebid meeting scheduled for July 30th and Bids due September 12th.
07/30/24 – Prebid meeting completed.
08/29/24 – Addendum No. 1 to be published.
08/29/24 – Addendum No. 1 published.
09/09/24 – Addendum No. 2 published.
09/19/24 – The bids were received from Browning Chapman and Buckeye Construction and Restoration. Both bids were under budget and within 8% of each other.
09/25/24 – THP and Browning Chapman had bid review meeting. BC appears to have all major scope items covered, including site logistical needs. The group discussed extending the contract to include time this winter to allow for shop drawing and window fabrication. BC is reaching out to the subcontractors to determine feasibility and needs. THP to publish summary letter after BC determines the needs.
10/08/24 – THP published the bid summary letter recommending Browning Chapman based on the bid amount.
10/31/24 – Hamilton County working on the AIA contract.
12/11/24 – Contract before the BOC for execution.
12/11/24 – Contract before the BOC for execution.
12/17/24 – Contract approved and sent to BC.
01/30/24 – Project status – BC finalizing submittals and background checks. Preconstruction meeting scheduled for 2/18/25. Anticipated construction starting end of March.
02/17/25 – Browning Chapman sent submittals for THP’s review.
02/18/25 – Preconstruction meeting completed.
2/27/25 – Browning Chapman finalizing background checks, submittals and permitting. THP working on submittals.
3/11/25 – Progress Construction Meeting.
3/18/25 – Progress Construction Meeting.
3/24/25 – Browning Chapman mobilized.
3/25/25 – Progress Construction Meeting.
3/26/25 – THP finalizing revised submittals and reviewing pencil Pay App #1.
04/01/25 – Progress Construction Meeting.
04/08/25 – Progress Construction Meeting.
04/09/25 – Permit Issued.
04/15/25 – THP finalized all submittals.
04/15/25 – Progress Construction Meeting.
04/21/25 – Roofing demo and window removal on East Skywalk began.
04/22/25 – Progress Construction Meeting.
05/06/25 – Progress Construction Meeting. East Skywalk roofing.
05/13/25 – Progress Construction Meeting. East Skywalk roofing complete. Steel Installation. North Skywalk mobilization.
05/20/25 – Progress Construction Meeting. East Skywalk steel painting, window flashing, painting mock-up. North Skywalk stair scaffold and roofing on east portion.
05/27/25 – Progress Construction Meeting. East Skywalk window installation. North Skywalk roofing and window removal/temp. panels on east portion.
06/03/25 – Progress Construction Meeting. East Skywalk Window install complete. North Skywalk Roofing east half complete and window removal/angle install in progress.
06/10/25 – Progress Construction Meeting. East Skywalk Façade painting in progress and North Skywalk roofing west half in progress.
06/17/25 – Progress Construction Meeting. North Skywalk Roofing west half complete and window removal complete. North Skywalk window install in progress. Punchlist started.
06/24/25 – BC sent Pencil Pay App #4 for review. THP to return shortly.
07/15/25 – Progress Construction Meeting. North Skywalk Façade painting.
07/29/25 – THP issued punch lists for North Bridge roof work and East Bridge. North bridge roof work was completed.
07/29/25 – Progress Construction Meeting. North Skywalk Façade Painting complete. East Skywalk Punch Complete. EJ Work in progress. BC sent Pencil Pay App #5 for review. Final Punch scheduled for 8/14/25 @ 1pm.
08/15/25 – THP investigated reported leak condition on the east end of the north bridge.
08/18/25 – BC, THP, and County completed water test and confirm leak was from roof drain line in the cavity below the bridge slab at the east end of the bridge.
08/19/25 – BC and THP used a camera to scope the drain line and found two breaks in the drain line that corresponded to the leak location.
08/21/25 – BC, THP and County completed punch trip for north bridge.
08/28/25 – THP exploring different plumbing repair options and developing opinion of probable costs.
10/29/25 – BC to begin Roof Drain line repair on 11/03/2025. 2 week schedule.
11/06/25 – THP completed site visit to review completed drain line.
11/14/25 – THP reviewed hatch mockup. Proposed hatch too big for panel. Updated panel size ordered. Weather permitting panel work to start in December.
12/11/25 – BC is installing the access hatch in the panel at the shop. Painter is scheduled to paint the panel in the shop. Once complete, BC to schedule panel installation.
01/28/26 – THP is reviewing BC’s Closeout Documents and should be returned 01/30/26.
01/28/26 – BC is currently estimating repairs for Concrete truck damage to North Skywalk.
02/05/26 – THP returned all Closeout Documents with comments to BC for final submittals to HC.
02/25/26 – THP to reach out to Imbus regarding mental panels and bending 20′ lengths.
03/25/26 – North Skywalk leak – BC indicated they are in contact with Delaware glass.
03/25/26 – Concrete truck panel damage – BC reaching out to metal panel manufacturers to get custom panel pieces and working up pricing. BC would like to coordinate panel repairs with leak.
04/20/26 – BC sent proposal to THP for Metal Panel Repairs. THP to review proposal with HC and schedule the work.
04/28/26 – BC is working with Delaware Glass on the leak at the North Skywallk and is working on scheduling them next week. A lift is required and will need to be delivered.
05/11/26 – Lift Plan submitted for Metal Panel work and glass warranty work.
05/19/26 – BC submitted cost breakdown for skywalk repairs to HC.
06/25/26 – Delaware Glass has completed warranty work for leak in North Skywalk. BC has completed metal panel work at North Skywalk and has processed all requested closeout documents.
07/30/26 – Verify with County if project can be archived.
09/23/26 – THP completed a site visit on 9/16/26 to review paint peeling on exterior skywalk façade. Field report to follow shortly.
10/26/26 – BC scheduling a site visit with Painting Contractor to review paint Issue.
10/28/26 – HC received letter from City of Cincinnati Permit District Inspector regarding open inspections for the project. BC was notified.

JC – Skywalk Roof Replacement & Exterior Repairs (F002) Read More »

2020 – Slab and Masonry Repairs (F001)

PM: Rycca Thacker, Paul Bellman
02/01/24 – Hamilton County requested slab project be rebid based on previous project.
02/12/24 – THP published review documents to the County.
02/16/24 – Hamilton County provided review comments to the documents.
02/16/24 – THP published bid documents to Hamilton County.
02/20/24 – Hamilton County advertised project for bid.
02/27/24 – Prebid meeting occurred.
03/11/24 – Addendum 1 issued to Purchasing.
03/14/24 – Addendum 2 issued to Purchasing.
03/15/24 -Addendum 3 issued to Purchasing.
03/28/24 – Bids due date April 8, 2024.
04/12/24 – Reviewed Bid with Browning Chapman.
04/19/24 – THP issued Bid Summary Letter to Hamilton County.
05/02/24 – Hamiliton County issued Contract Documents to Browning Chapman.
05/10/24 – Browning Chapman returned signed documents.
05/30/24 – Hamilton County Board review on 06/06/24.
07/19/24 – Browning Chapman working on pricing estimates for floor finishes, submittals, and background checks.
07/23/24 – Hamilton County requested to schedule a kick-off meeting.
08/15/24 – Preconstruction meeting completed.
08/19/24 – THP issued meeting minutes.
08/28/24 – Browning Chapman issued revised flooring options estimates. Browning Chapman’s submittals approved. Project to be scheduled.
09/25/24 – Browning Chapman submitted new flooring proposal for polished concrete. Approved and BC will need to develop Change Order.
10/28/24 – THP returned submittals to Browning Chapman.
10/31/24 – Final Pre-Construction meeting scheduled for Friday 11/01/2024.
11/01/24 – Kick-off meeting.
11/04/24 – HC sent Notice to Proceed.
11/07/24 – Progress Construction meeting.
11/14/24 – Progress Construction meeting.
11/20/24 – Progress Construction meeting.
11/20/24 – THP Signed Pay App #1 and sent to HC.
11/27/24 – Progress Construction meeting.
12/05/24 – Progress Construction meeting.
12/10/24 – THP signed Change Order #1.
12/12/24 – Progress Construction meeting.
12/13/24 – THP Signed Pay App #2 and sent to HC.
01/09/25 – Progress Construction meeting.
01/16/25 – Progress Construction meeting.
01/23/25 – Progress Construction meeting.
01/23/25 – THP Signed Pay App #3 and sent to HC.
01/30/25 – Progress Construction meeting.
02/13/25 – Progress Construction meeting.
02/20/25 – Punchlist Walkthrough.
02/26/25 – Browning Chapman finalizing punch list items. Final walkthrough scheduled 03/06/25.
03/06/25 – Final Walkthrough and signoff of completed items.
03/07/25 – THP signed Pay App #4 and sent to HC.
03/26/25 – Email sent to Browning Chapman requesting Closeout documents. BC indicated Closeouts will be ready for review on 3/28/25.
04/11/25 – BC sent closeout documents to THP for review.
04/18/25 – THP sent reviewed closeout documents and comments back to BC.
04/22/25 – THP sent HC signed Pay App #5 – Final Retainage.
04/24/25 – BC sent HC Final Closeout Documents.
05/29/25 – Can THP archive project?
06/25/25 – Project Archived.

2020 – Slab and Masonry Repairs (F001) Read More »

A&D – First Floor Drinking Fountains

PM: Rycca Thacker, Terry Cannon
02/01/24 – Create project for single upgrade of core area drinking fountain.
02/23/24 – Met onsite to review existing conditions. Champlin putting SOSS together for TTE to use for SOSS to county for one EWC on first floor. Build out into Security space seemed doable.
03/19/24 – SOSS submitted for approval, full scope.
03/22/24 – Fees seemed high for single drinking fountain, second SOSS submitted with reduced scope.
04/24/24 – On hold waiting on direction from County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold. Ready to archive.

A&D – First Floor Drinking Fountains Read More »

2020 – Locker Room Buildout

PM: Jesse, Sam, Terry
02/01/24 – Champlin to send SOSS to TE for this job for Design, Bidding and Construction.
02/29/24 – Kickoff Meeting to be scheduled in near future.
03/28/24 – Kickoff held. Project to be bid in the next month or two.
04/25/24 – Bid Schedule needs to be determined. Project ready to move forward with small project bid. At the Partner Meeting we decide to have Trades do the work, TTE and CHA will assist with permitting. No sprinkler work needed. minimal HVAC. We do need an IBI and General Permit.
05/30/24 – Estimate to be sent to John. CDs in progress.
06/27/24 – Drawings and Estimate sent to John. Permit can be submitted when necessary.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – Permit to be submitted next week.
01/30/24 – Electrical Permit returned. Building and Mechanical Permit in progress.
02/27/25 – Building and Mechanical permit approved.
03/27/25 – No update.
04/24/25 – County to submit trades as a certified contractor in City of Cincinnati.
05/29/25 – No Update. County is getting Trades registered, trying to get fellow government entity set for this work.
06/26/25 – Trades is registered with the city but the HVAC work would not be allowed to be self performed. HVAC scope will be removed and permit revision submitted. ThermalTech updating the HVAC for engineering revision.
07/31/25 – City is not allowing any work that even touches HVAC to be done without a licensed HVAC contractor. We will need to bid out at least the HVAC work. Follow up at meeting was to remove the ceiling from the permit set and any work not associated with the wall and door going in. Resubmit permit without additional work.
08/28/25 – All ceiling work has been removed from the project. Permit approved and ready for pickup.
09/25/25 – No Update.
10/30/25 – Trades have began work. In wall inspection complete and board can be put up.
12/11/25 – No update.
01/28/26 – Work is complete.

2020 – Locker Room Buildout Read More »

A&D – Mother’s Room Upgrades

PM: Rycca Thacker, Terry Cannon
01/22/24 – Fieldwork rechecked, owner review set by Friday.
01/31/24 – Drawings sent to Rycca for review. We will assist with permitting through the City of Cincinnati and with install as needed by Trades.
02/23/24 – County reviewing drawings.
03/22/24 – Still on hold.
04/24/24 – On hold waiting on direction from the County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
12/31/24 – HC said to archive this project.

A&D – Mother’s Room Upgrades Read More »

JC – Underground Fuel Tank Replacement 2024

PM: Matt Butz, Terry Cannon
01/24/24 – Project created for tracking any 2024 updates.
02/23/24 – Drawings are created for this year’s bid.
03/22/24 – TTC to create new SOSS in the hopes this job bids again this year.
04/24/24 – TTC has not submitted the SOSS for this job yet. Not sure it needs one, ask on Thursday.
05/29/24 – One of the first steps is to engages Terracon to scan the parking lot around where the new underground tank will be located for anomalies.
06/26/24 – TTC will get Terracon scheduled for July hopefully.
07/24/24 – Terracon has been asked to update their proposal. No SOSS has been submitted for 2024 project yet.
08/28/24 – Revised proposal received today, TTC to review.
09/24/24 – Project will now be rolled up with Emergency Power updates and their next bid.
10/30/24 – Archived.

JC – Underground Fuel Tank Replacement 2024 Read More »

SPHQ – ALC Upgrade BAS Commissioning 2024

PM: John Nester, Terry Cannon

01/24/24 – Post created for tracking.
01/31/24 – Two punchlist sent to ALC for work on the current job. Training scheduled for Friday with Mike Bowman and Emcor.
02/02/24 – Training went well. Ian, Kendall, Curtis, Terry and Barrett attended. We made a few adjustments while reviewing.
03/22/24 – Project completed, just waiting on some summertime use before we close it out.
04/24/24 – Emcor onsite this week trying to get AHU-1, AHU-4 worked out for dual circuiting. AHU-1 VFD installed on 4/23. NKYHC replacing refrigerant and ambient.  Emcor wrapping up they Comm Center and starting the 250 WHT building next week.
05/29/24 – Controls work has been completed and VFD installed. We need to check back with Ian to see if its working better.
06/26/24 – DK currently working at 250, will check on progress.
07/24/24 – 250 WHT is almost complete. 486 next, then Comm Center. TTC checks the graphics and there is work to do before we say they are done.
08/28/24 – Working on final stages of 250 WHT.
09/24/24 – 250 WHT graphics are not complete, points are being programmed now. SPHQ appears that most upgrades are complete. Comm Center graphics are intact but no space temperatures are shown on floor plans, none of the mechanical equipment is shown on a site plan anywhere, found it in the Basement but there is no chiller shown on the plans. Public Works Garage has updated controls on the new work from the renovation has not been programmed and we have no feedback on space temperatures yet. The Records Center has no space temperatures on graphics.
10/30/24 – All buildings are complete except for Records Center according to Emcor. They are waiting on an outdoor enclosure for the outdoor RTU.
12/12/24 – TTC reviewed SPHQ and asked that Emcor put space temperatures on the floor plans with the thermal graphics maps like we did at SPHQ.
01/28/25 – Progress ongoing. All buildings are either done or partially complete. Price received for temps on floors and passed along to Tony for consideration.
02/26/25 – TTC reached out for an update from Mike and Steve yesterday.
02/27/25 – Emcor received final IP address for last building. Mike Bowman will be out to add the last building and then TTC to punchlist.
03/25/25 – ALC should be complete with all buildings. TTC will create a punchlist for each building in the next 30 days.
04/23/25 – TTC working on punchlist right now.
05/28/25 – Archived.

SPHQ – ALC Upgrade BAS Commissioning 2024 Read More »

230 – COA Camera System Upgrade 2023

PM: John Nester, Mike Barth
12/06/23 – TEI receives approved SOSS and PO.  COA to provide TEI with locations of cameras that were discussed with vendor.
01/30/24 – TEI to receive the locations and document on documents.
02/28/24 – TEI will document locations upon receipt.
03/27/24 – TEI, HCFD and DK meet, document locations, and develop drawing.  Meeting with all team on 03/26/24 to review and finalize.
04/24/24 – Installation pending material procurement.
05/29/24 – Completion of this project pending punchlist once TEI notified all install work is complete.
06/26/24 – Cameras are installed and the users are working on getting the monitoring functioning (instructions from installer (DK) via email), and Matt Butz helped with Valerus integration to allow end users to utilize the system.
07/24/24 – TEI and HCFD perform punchlist on the project. Tenant confirms views are as desired.
08/28/24 – Project complete pending closeout documents.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

230 – COA Camera System Upgrade 2023 Read More »

JC – Exterior Camera System Upgrade 2023 Part II

PM: Matt Butz, Mike Barth
12/06/23 – TEI receives signed SOSS.  Design kickoff to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to kick off project.  Locations and desired coverages discussed.  TEI can develop documents based on meeting on 01/30.  Roof camera replacements are first priority.
02/28/24 – TEI developing plans based on meeting.  Will coordinate the issuances with HCFD.
03/27/24 – Drawings to be completed in April/May.
04/24/24 – Drawings in process.
05/29/24 – No updates
06/26/24 – TEI hand delivers drawings to HCFD for review.
08/28/24 – Project complete pending closeout documents.
12/12/24 – OK to Archive.

JC – Exterior Camera System Upgrade 2023 Part II Read More »

Hillcrest – Door Access and Camera System Upgrades

PM: Matt Butz, Mike Barth
02/28/24 – TEI, HCJC, and HCFD meet on site to discuss the project objectives and locations where coverage is needed.  Review set to be sent to HCFD on 3/1/24.
02/29/24 – Jaime will get Mike a set of review drawings EOD today, sent to Matt tomorrow hopefully.
03/27/24 – Documents completed and Dent to HCFD.  Meeting with Juv Ct, HCFD, Telecom, and Jason/Todd on site to review and adjust.  Documents completed for installation.
04/24/24 – installation pending material procurement.
05/29/24 – TEI has received no updates. BW asked if O’Rourke has provided any of county paperwork yet? Answer, no.
06/26/24 – DK arrives on site to begin installation.  Installation ongoing. Risk Mgmt has decided that the NVR will be located on the downtown campus and feed will come back downtown.
07/24/24 – HCFD and TEI to perform punchlist pending HCFD availability.
10/31/24 – Need change order to relocate NVR to Security Bldg.
12/11/24 – Punchlist issued and DK sends back signed completed punchlist.
02/26/25 – project complete pending final closeouts.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.

Hillcrest – Door Access and Camera System Upgrades Read More »

230 – Access Control System Upgrades 2023

PM: Matt Butz, Mike Barth
12/06/23 – TEI issues SOSS.
01/30/24 – TEI receives signed SOSS and PO.  Project documents to proceed.
02/28/24 – Project is ongoing
03/27/24 – On site investigation  and kick off meeting with DK occurred on 03/26/24
04/24/24 – Review set will be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD review.
07/24/24 – Construction completed. HCFD and TEI completed punchlist walk.
08/28/24 – Project pending closeout documents.
12/11/24 – No Updates
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – Archive.

230 – Access Control System Upgrades 2023 Read More »

TPC – Access Control System Upgrades 2023

PM: John Nester, Mike Barth
12/06/23 – TEI submits SOSS.
01/30/24 – TEI receives signed SOSS and PO.   Project to Proceed.
02/28/24 – TEI and HCFD discuss project schedule based upon system needs (existing system failures and parts unavailability).  TEI commits to getting project upon MCB return from medical issues.
03/27/24 – Project in the works.  TEI Submits SOSS for Small Projects bid for installation costs
04/24/24 – Project documents in progress.  review set to be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small bids project bidding. Prebid meeting conducted. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received opened for project (2 bids, Glenwood and DK). DK apparent low bid. TEI vets bid on 08/28/24.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for preconstruction meeting. Anticipated start date at completion of Jax cameras (Mid December)
12/11/24 – Construction to commence upon completion of the JAX camera Project.
01/29/25 – Project construction kick off occurred on 01/28/25. Construction to commence upon receipt of people to integrate into the system and access levels from Risk Mgmt.
02/26/25 – Construction ongoing on this project.
03/26/25 – Construction complete. HCFD and TEI perform punchlist.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – No updates.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.

TPC – Access Control System Upgrades 2023 Read More »

Hillcrest – Birch Cottage Removal (F095)

PM: Bert Watts, Paul Bellman
09/28/23 – Hamilton County requested SOSS.
10/30/23 – THP provided SOSS for review.
11/20/23 – County approved SOSS.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/22/23 – THP issued 90% Drawing Owner Review set to Hamilton County.
02/16/24 – THP issued Bid Documents to Hamilton County.
02/20/24 – Hamilton County Purchasing advertised documents to bid.
03/04/24 – Pre-bid meeting held.
03/19/24 – Addendum 1 issued to Purchasing.
03/28/24 – Bid opening scheduled for April 10, 2024.
04/18/24 – THP scheduled Bid review with O’Rourke for 04/25/24.
05/16/24 – Hamilton County requested documents from O’Rourke.
05/30/24 – THP to follow up with requested documents (Schedule of Values, Schedule, Safety plan, general submittals) and schedule pre-construction meeting.
06/05/24 – THP emailed O’Rourke regarding submittals and Pre-construction Meeting.
06/25/24 – THP sent follow-up email to O’Rourke.
06/26/24 – Hamilton County received Asbestos Inspection – Notice of Compliance. O’Rourke to start sending submittals on plumbing material and valves in conjunction with other things.
07/16/24 – Pre-Construction meeting held.
07/17/24 – Pre-Construction meeting notes distributed to all parties. Mobilization scheduled for 7/29/24 (tentative).
07/29/24 – Mobilization and utility work started.
08/16/24 – Demolition complete.
08/23/24 – Final grading complete.
08/28/24 – Seeding and strawing postponed – hold retainage. THP to review pay-app.
09/12/24 – Hamilton County and THP – Final Site walk through.
09/19/24 – THP issued Field Report.
09/25/24 – THP issued closeout list to O’Rourke.
10/09/24 – O’Rourke issued Closeout Documents to THP.
11/27/24 – THP sent pencil copy of Closeout Documents to Hamilton County for approval.
12/10/24 – THP sent final Punch List to be signed and notification for payroll documentation.
12/11/24 – O’Rourke is sending Closeout Documents to Hamilton County.
12/13/25 – Closeout Documents sent to Hamilton County.
01/03/25 – Finalizing Final Pay Application for retainage.
02/26/25 – No updates on Certified Payroll from O’Rourke/Park’s Electric.

Hillcrest – Birch Cottage Removal (F095) Read More »

THP 2024 General Services (F093)

PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
02/29/24 – Record Center roof was noted to be leaking in a number of locations. Roof is under warranty. THP documented the conditions and met with the manufacturer and contractor. Manufacturer’s warranty department has approved a repair approach. Contractor is pricing.
02/29/24 – 800 Broadway tile in NE stair tower had cracking at the first floor level. THP coordinated contractor stabilization, removal and repair. Repair is complete. THP to provide a summary report.
04/25/24 – THP no update.
06/27/24 – Record center roof repair started today and is planned for the next 2-3 weeks. THP scheduled to be on site Friday to review progress.
07/12/24 – Tremco completed warranty repairs and submitted reports for review.

THP 2024 General Services (F093) Read More »

CH – Vestibule Air Curtains 2023

PM: Jesse Estes, Terry Cannon
09/21/23 – Tony requested SOSS for this work. Replace all three he confirmed in a phone call with him.
09/27/23 – Working on SOSS today.
10/25/23 – Review set will be ready Friday for owner review.
12/06/23 – Bids received from DK and Triton. DK is the apparently low bidder. Tony suggested accepting only the Alternates to add heaters to the left and right vestibules. TTC will review the bids with DK and recommend the award for this project.
01/11/24 – DK submitted additional paperwork for this project per request.
02/23/24 – Contract under review.
03/22/24 – Contract under review.
04/24/24 – Contract in for final review.
05/28/24 – Stamped permit drawings sent to DK for permitting.
05/29/24 – Setup kickoff meeting with AJ, Tony, Tyler for starting this project.
06/23/24 – Pre Const meeting held, coredrill complete, team met on door swing issue this morning.
06/26/24 – DK reported that heater was deeper than the door swing and submitted an RFI for resolution.
06/28/24 – A top cap “box” solution was given to DK for pricing. This would move the heater up high enough for the door to open.
06/30/24 – IBI Issued the electrical permit. CIC2402080
07/08/24 – TTE requested factory review of the proposed box solution for the heater depth issue.
07/09/24 -The factory reported that we did not have enough clearance for proper airflow and TTC discovered the maintenance access was blocked by the proposed design.
07/10/24 – A revised solution was sent to the County for comment that moves the heater on top of the panel.
07/24/24 – TTC checked back on the revised design and it was accepted by Tony Matre, TTC forwarded to DK for review. Tyler inquired about still using the box solution.
08/28/24 – Left and Right heaters are installed. Reviewed and approved by TTE and Facilities. DK engaged for change order revision on the center heater in the middle vestibule with the exact same unit the left and right has. DK agreed CO#1 using the allowance monies to pay for the additional heater. Paperwork signed and sent to AJ this week.
09/23/24 – The left and the right heaters are installed, painted, and electrified. The center heater was ordered via change order and should ship 10/2. Once the third heater is installed the electric and controls will be finished for all three heaters.
10/30/24 – All three heaters are installed. Two of them have power and final paint. AJ trying to get electrician on site to power up the final heater. AJ lining up Joe Bulach for DDC integration after third heater is ready.
01/02/25 – Controls are installed, all heaters should be working, punchlist sent, contractor has been asked to start closeout on this project. The heaters are discharging about 110F.
01/27/25 – Still waiting on final closeout documents from contractor.
02/26/25 – Closeout Documents almost complete., they are coming in.
03/25/25 – Closeout documents received and final pay apps being processed.
04/02/25 – Jesse Submitted final pay app today.
04/23/25 – Project can be archived.

CH – Vestibule Air Curtains 2023 Read More »

Hillcrest – Conditions Assessment 2023

PM: Bert Watts, Mike Murphy
07/12/27 – SOSS approved, kickoff meetings scheduled.
07/17/23 – Fieldwork started with Architect & MEP. Cottages will be first.
07/27/23 – All fieldwork is completed. Top 10 list has been shared. Champlin working on consolidated list. County will take control of site on 8/1/23 per email.
08/31/23 – Pavement condition report and tree maintenance report have been received. Architectural report nearly complete. MEP system report sample draft of some buildings has been received and acceptable. Other buildings in process. On target for mid September submission.
09/12/23 – Sent final reports to Champlin for Hillcrest including cost estimates for use on final report.
09/28/23 – Final report submitted to County
10/25/23 – Champlin to provide estimate for interior painting of cottages.
02/01/24 – Ready to Archive.

Hillcrest – Conditions Assessment 2023 Read More »

2024 Project Cost Estimates

PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.

2024 Project Cost Estimates Read More »

A&D – Digital Clocks

PM: Rycca, Barth
07/27/23 – County requested SOSS for this project.
08/24/23 – TEI submits SOSS.   Project pending SOSS approval.
09/26/23 – Project Pending SOSS Approval.
10/26/23 – Project pending SOSS Approval.
12/06/23 – Project pending SOSS Approval.
01/30/24 – TEI receives signed SOSS and PO.  Project proceeding with Documents.
02/24/28 – No updates on this project this month.
03/27/24 – Project waiting on direction from HCFD.
04/24/24 – Project pending direction from HCFD.
05/29/24 – No updates.
06/26/24 – No Updates.
07/24/24 – No Updates.
01/30/25 – Ok to Archive this project.

A&D – Digital Clocks Read More »

JC – Façade Monitoring 2023 (F087)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 11th.
10/03/23 – Field survey of façade started.
10/11/23 – Rappel of façade completed.
10/26/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
07/25/24 – THP completed assessment and report. No work needed. Final City report due 07/01/27 – Ready to Archive.

JC – Façade Monitoring 2023 (F087) Read More »

2020 – City Façade Monitoring 2023 (F086)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/06/23 – Rappelling of façades completed.
09/28/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update
08/29/24 – No repairs needed final report due next June.

2020 – City Façade Monitoring 2023 (F086) Read More »

800 – Annual Façade Monitoring 2023 (F085)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 10th.
10/10/23 – Rappelling survey of Tower completed.
10/17/23 – East wing loose debris survey started.
10/19/23 – East wing loose debris survey completed.
10/26/23 – THP working on summary report updated.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/26/24 – Monitoring updated report submitted.
06/27/24 – Budget submitted to County.
08/29/24 – THP scheduling façade knock down survey and inspection for 2024.
09/26/24 – THP to review knock down approach with larger repair package.
10/31/24 – Ready to archive.
12/10/24 – THP closing out the project.

800 – Annual Façade Monitoring 2023 (F085) Read More »

A&D – Annual Facade Monitoring 2023 (F084)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/06/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 3rd.
10/03/23 – THP completed rappelling and façade monitoring survey.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
08/29/24 – THP working on repair package for City repairs.
12/10/24 – THP closing out the project.

A&D – Annual Facade Monitoring 2023 (F084) Read More »

CH – Backflow Preventer Replacement

PM: Jesse Estes, Terry Cannon
04/18/23 – Request for SOSS to replace BFP at CH
05/05/23 – SOSS submitted.
06/21/23 – Fieldwork scheduled.
06/29/23 – We decided to bid this job Small Project given our previous experience with the JC BFP. Project submitted for final review to John.
07/26/23 – Final drawings being prepared, we will add two shutoff valves ahead of the BFP when they are replaced. We should be able to get this bid out within the next month.
08/29/23 – Project is ready for XBE. TTC to prepare for bidding.
09/27/23 – We are putting together front end documents together for this bid now.
10/25/23 – Addendum 1 ready to go out today. Bids are due 10/31.
12/06/23 – Bids received and vetted by ThermalTech. DK was the apparent low bidder and was recommend for award. Contract and PO approval stage.
01/17/24 – Additional paperwork requested by John Nester for this project.
01/24/24 – TTC contacted Bill Roach again for bid documents.
01/31/24 – Nothing received yet.
02/23/24 – Waiting on contract documents from DK.
03/22/24 – Contract under review.
04/24/24 – Contract signed by DK, County waiting on insurance from DK. Submittals were received and sent back for updates. The revised submittals were received today and sent back to the County and put back in the queue for TTE review.
05/28/24 – PO and Contract ready, setup kickoff meeting with DK and County.
06/26/24 – Pre Const held last week. DK has equipment in stock. We need to decide on a couple of valve questions before DK gets started.
07/01/24 – Pre Const meeting minutes distributed to the group. the BFP are in town and the work can be scheduled with HamCo on their schedule. No payapps or SOV has been received or approved yet.
08/28/24 – DK waiting on one more background check to clear and then they will schedule the work.
09/24/24 – Last DK worker did not make it through background checks. DK preparing to do the job with three workers. Bill setting up new schedule.
10/30/24 – Bill ready to do work in November, December time frame with three plumbers over two weekends. He will pick the weekend and give us a scheduled soon.
12/12/24 – The West BFP Replaced last week plus the two isolation valve above the city water booster pump. A small leak was discovered in the West BFP. GCWW does not know where the main city water shutoff is on the east side of the Courthouse so they are doing more fieldwork this week. DK will be after the holidays to do the next BFP. We received work from the city water inspector that the BFP clearances from the floor are acceptable.
01/28/25 – GCWW still searching for east side shutoff valve for east BFP. We are getting conflicting data about the exact location of the existing valve. Regardless it appears as thought GCWW would like to replace this valve when found. One valve found in the street apparently has bad packing, this valve would also be replaced. We will continue to coordinate and get updates from DK and keep the County up to date.
02/26/25 – Still waiting on GCWW to located and fix East Side main shutoff.
03/25/25 – HamCo provided updated from GCWW about locating and find the East shutoff valve for the building. As soon as that is located we will proceed with the next phase.
04/23/25 – GCWWW has scheduled multiple visits to fix or replace the Courthouse isolation valve for the East side of the building. As of this meeting, it is not complete. DK is checking in weekly with GCWW for updates. The DK change order has been submitted for the spool piece leak repair.
05/28/25 – DK meeting GCWW on site Friday to verify the new shutoff valve is holding. Then they will scheduled BFP replacement with County including the new spool piece.
06/01/25 – Will spoke with Justin at DK and have the following update to our never-ending waterworks saga. The isolation valve in the street has been replaced by GCWW. They haven’t patched the road yet so there’s no access to the valve without a backhoe to remove the road plate. DK will wait until the road is patched before performing work(expecting sometime this week or next week for that to take place). At the earliest, DK may replace the backflow preventer next Friday. They’ll be in touch to schedule the work.
06/25/25 – Second BFP replaced last Friday. Spool piece replaced at the same time. Everything seems to be working correctly.
07/28/25 – Both backflow preventers are replaced. TTE needs to do a final punchlist and verify final invoices before closeout.
08/26/25 – Punchlist complete and sent to Debra for signature and updates.
09/24/25 – Checking in with DK weekly for closeout and approvals.
10/29/25 – No closeout paperwork or additional communications from DK have been received. We reached back out for an update. Billy was out 10/6-10/10.
12/12/25 – Ready to Archive. Final documents being delivery to Jesse on 12/13.

CH – Backflow Preventer Replacement Read More »

Dane – Phase 2 Renovations

PM: Bert Watts, Mike Murphy, Terry Cannon
06/29/23 – Opened for tracking.
07/27/23 – Cad plans are ready per request.
08/31/23 – New SOSS requested and will be submitted this week.
09/01/23 – Sent SOSS to Champlin for use on 152 and 157 Kennel options. TTE started working on a zoning and load calc for any future dehumidification unit we may need.
09/28/23 – Small Project flooring replacement ready for bid. Project will be sent out 10/3.
10/25/23 – Bids received for Epoxy Flooring Installation. Bid vetting in progress. Trench drain scope in progress.
10/26/23 – TTE requested design meeting with owner to review HVAC requirements for this space. Temporary vs new conditions, reusing existing equipment, locations of new equipment.
12/07/23 – User meeting held to discuss phase breakdown. Phase 1 = Epoxy Flooring. Phase 2 = Plumbing Improvements. Phase 3 = HVAC Improvements. Phase 3 = All other improvements. Phase 1 has contract signed and flooring installation scheduled for 1/29. Phase 2 to be submitted for owner review 12/15.
01/31/24 – TE submitted Plumbing and HVAC review drawings for this project concerning the trench drains and air conditioning systems for this phase of upgrades. We are still exploring most economical ways to build these trenches at the Dane St. site.
02/29/24 – Request for availability for final phase II meeting sent out. Waiting to hear back from Cares. We can be ready for bid end of March. Wait until next Wednesday and set the meeting with available data.
03/28/24 – Final review meeting held. Cares requested consultant to review the plan. Shelter Planners of America have been brought on and will conduct review.
04/25/24 – Consultant brought on board for industry standard advice. Updated plan presented to CARES. Champlin to incorporate changes and determine new phasing plan.
05/30/24 – Drawings have been updated to reflect plan changes for Phase 2. Final estimate to be submitted this week. BW said to go ahead and include the kennel cost in the Phase 2 work. Phase 3 cost due end of June to County as well. Coordinate with structural for final design and cost.
06/27/24 – Phase 2 and 4 cost submitted to Bert. THP investigated structure options for Phase 3. It was determined that the best option is to put the mechanical units on a platform behind the building that will later serve as the sallyport structure. Goal is to have Phase 2 & 4 ready for bidding by July 17. Phase 3 to be purely HVAC scope and okay to include platform & roof now in this phase. OK to pour slab during this phase. Stairs and ramps can be done later. TE will put power in for Portable HEPA to hold us over until the new units are installed on the new platform in Phase 2.
07/12/24 – Phase 2 & Phase 3 cost submitted to Champlin for rollup to County and Cares.
07/23/24 – Phase 2 + 4 Issued for Bid with additional work included as alternates with latest request from owner and tenant.
08/29/24 – Phase 2 bid opening 9/3. Acoustical vendor bids came in and Universal had the lowest bid for this project.
09/26/24 – Phase 2 bids awardable. Contract returned. First submittals received.
10/31/24 – Contract finalized. Scope may change slightly due to record center work. Holding off on permit submission until changes are finalized. JN said pick a new material for the walls and change them to something less permanent. We discussed phasing for Dane vs Records at this meeting and the fast timeline of preparing space for Phase 2 work for the dogs.
12/12/24 – Bulletin #1 issued addressing scope change requests. Submittals are in process. Kickoff meeting scheduled for next week.
01/30/24 – Bulletin #1 was rescinded. Bulletin #2 issued with minor changes to account for the cancellation of Phase 3. Applying for a change of use in Zoning is ongoing. Application has been sent to examiner for review. Once his comments are received, we can apply for a conditional use review. Permit will be held up until zoning is complete.
02/26/25 – Bulletin #2 and #3 have been issued. Zoning hearing scheduled for March 12. Work ongoing.
02/27/25 – City zoning link was sent to Rycca and Champlin and Nester, not allowed to share, but BW will join with JN. Other witnesses can request access 24 hours in advance.
03/27/25 – Zoning conditional use was approved. Building department has not issued the permit yet and the building department has ordered a halt on all work until a permit is approved.
04/24/25 – Permit has been approved and work resumed. Kennels were delivered on site. We are still on schedule to be complete by end of June.
05/29/25 – Phase 1 punch scheduled for 6/2. Phase 2 work complete by end of June.
06/26/25 – Fire alarm and electrical issues pushed back turn over of phase 1. Phase 2.1 punch complete.
07/31/25 – All punch work is complete. The exterior ramp begins next week. Closeouts to be submitted by Graybach.
08/26/25 – Project is complete. TTC working with Ian and Chris on Wi-Fi thermostats. RTU-7 does have issues but wasn’t part of project. Ian getting . Entrance ramp poured incorrectly. Corrected railing detail to be provided to Graybach.
08/28/25 – Ian getting prices to replace RTU-6,7 given the issues. JN said CVW met with CARES on the security camera, JN to get AIA, TTE to send XBE forms, keep this moving ASAP.
09/25/25 – Multiple issues with all washers. Supplier and plumber met onsite to discuss issues. They are being replaced. Railing work outstanding. Graybach to submit closeouts in next 2 weeks. Security Camera project to be in to John for review by Monday.
10/30/25 – Railings installed. Punch list sent to Graybach and work completed. Back punch to take place in near future. Closeouts received but have not yet been reviewed.
12/11/25 – Railing punch items addressed. Closeouts reviewed. Graybach to provide missing items.
02/26/26 – Closeouts delivered to County.
03/26/26 – No update. County to review closeout documents.
04/30/26 – Final items to be delivered to County.

Dane – Phase 2 Renovations Read More »

Scroll to Top