Hamilton County Facilities

A&D – JFS 3rd UPS Upgrade REBID

06/23/09 – This project is complete. There were no punchlist items and all closeout documents have been received and sent to Bert.

06/03/09 – We received 2 pay applications today #1 & #2 and signed them and sent them to Bert. We have to write a $5000 deduct change order for the allowance since none of that was used for this project. Closeout documents received and approved by MH and mailed to Bert with the pay apps.

02/26/09 – Submittals are being held pending notification that the unit will fit in space from Ginter.

02/02/09 – Pre Const Mtg was held last week with Ginter.

12/04/08 – Contracts have been submitted for approval.

11/03/08 – Addendum 01 went out to bidders. Some calls were received about scope of work. TEI answered for bidders to match published information.

10/16/08 – Project cancelled and scheduled for rebid on October 28th.

08/25/08 – Pre Const Mtg is schedule for Wednesday. There is serious issues with Banta requesting more money. TTC spend a couple of hours this morning sending and compiling messages to Kathy & Sherry about this issue. Huntwork is handling the meeting.

08/22/08 – Kathy called to say contract is approved and we are ready to start the project. TEI will try to setup a kickoff meeting for next week.

08/04/08 – Kathy B reported contracts have been received. JFS will advise when project is ready to start.

07/30/08 – TEI has been told the contract is complete. Banta has contract and it is in the signing stages.

07/24/08 – Banta has requested additional funds for a delay in project start.