03/26/18 – GBBN contacted by Facilities to plan Kick-off Meeting with Community Development.
03/29/18 – Kick-off Meeting date and time decided.
03/30/18 – Kick-off Meeting held at Room #1022, 10th Floor, of CAB. Discussions held related to the requested scope.
04/03/18 – Facilities sends marked-up plan showing clarified scope for SOSS creation. Photograph of front desk sent later by Facilities to GBBN.
04/06/18 – Facilities clarifies card reader access system is desired by Community Development.
04/09/18 – TEI sends SOSS input to GBBN for SOSS.