COURTHOUSE Cafe Partition Renovation

Partner Lead: GBBN

09/09/14 – William Radcliff of the State of Ohio Opportunities for Ohioans with Disabilities contacts GBBN about a renovation project at the Cafe on the first floor of the Courthouse.

09/16/14 – GBBN completed the required Business Enterprise Price Quote and Form and sent completed forms back to William Radcliff.

09/19/14 – GBBN meets with William Radcliff on site to discuss full scope of remodeling and deliverables.

09/26/14 – GBBN sends final construction documents to William Radcliff as requested.

10/06/14- William Radcliff responds with approval of deliverables.

10/14/14 – GBBN sends Hamilton County Facilities/Purchasing Department Bid Form with language regarding Background Checks.

01/23/15 – GBBN visits City of Cincinnati Permit Center to stamp and sign final permit drawings.

01/28/15 – GBBN sends final invoice to William Radcliff of the State of Ohio Opportunities for Ohioans.