COURTHOUSE – Fire Alarm System Study

Partner Lead: ThermalTech

04/27/16 – ThermalTech Submitted SOSS to Bert Watts – SOSS was approved and PO issued to ThermalTech.

05/25/16 – TEI is instructed by Building Ops that the full replacement of the system will not be completed at this time and that the balance of the SOSS shall be used for CA assistance with Honeywell replacing the non functioning components only at this time.

08/23/16 – BW indicated at last months meeting that the replacement of the Fire Alarm System will be included in a project request with the Server Room Project when the Server Room Project commences.

12/29/16 – Awaiting direction from Owner on this and related projects.

02/22/17 – Awaiting direction from Owner on this and related projects.