COURTHOUSE Roof Y and Z Leak Investigation

Partner Lead: THP


05/05/17 – Hamilton County requested SOSS to investigate roof leaks on the Y and Z roofs along the west elevation.

05/25/17 – THP developing SOSS.

06/08/17 – THP issued SOSS for review.

06/26/17 – County approved SOSS.

07/27/17 – THP plans to schedule work second week of August.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6t and 7th floor spaces below roofs.

08/25/17 – THP visited site to do visual survey of roofs Y & Z, and interior of 6th and 7th floor spaces below roofs.

09/28/17 – Based on weather forecast, THP planning on conducting thermal scans October 3rd.

10/03/17 – THP documented roofs Y & Z using infrared camera.

10/06/17 – THP met Underground Detective to inspect all drains at roofs Y & Z.

10/25/17 – Roof cuts scheduled, weather permitting.

10/26/17 – THP visited site to perform investigative roof cuts.

11/28/17 – THP finalized draft of report summarizing findings and recommendations.